From: Jennifer Cline

Sent: Tue Sep 16 17:24:11 2014

To: Mike Penunuri

Cc: hai@curran-mcleod.com; Garrett Edmunds; Dan Huff

Subject: FW: New stamped water line plan

Importance: Normal

Attachments: image003.jpg; MRM Water Line Addition 9-12-14..pdf; Comments.docx;

 

Hi Mike-

Do you have any comments regarding this water main extension? Please see attached plans.

I have also included our comments for your reference.

Also, Hassan has reviewed these and commented that the existing water main, Phase 1 (Sheet 1), is only 6”. He suggested having you flow test the line to verify it will meet the demands of 1500 gpm. Is this something your crew can do?

Regards,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.829.6855 Ext. #218

F: 503.829.3676

image "file:///C:

From: Mitch Jorgensen [mailto:mjj@molalla.net]

Sent: Friday, September 12, 2014 4:38 PM

To: 'Jennifer Cline'

Subject: New stamped water line plan

Here it is. Please submit to your engineering. Thanks

Mitch Jorgensen, Pres.

image QCT/CCT #44362

Molalla Redi-Mix & Rock Products, Inc.

PO Box 555

Molalla, Or 97038

(503) 829-5555 x 15 office

(503) 829-5558 fax

(503) 969-3377 cell

mjj@molalla.net