From: Jennifer Cline
Sent: Wed Dec 30 16:49:50 2015
To: Dan Huff
Cc: Chris Link
Subject: FW: Molalla Ave. cross-section
Importance: Normal
Something to consider, let me know your thoughts.
Jennifer Cline, P.E. | Public Works Director
Licensed in OR, WA
117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038
O: 503.759.0218 | F: 503.829.3676
From: Chris Link [mailto:Chris.Link@msa-ep.com]
Sent: Tuesday, December 29, 2015 8:38 AM
To: Jennifer Cline <jcline@cityofmolalla.com>
Cc: Hash, Kenneth F. <HashK@hdjdg.com>; Randall Stark <Randall.Stark@msa-ep.com>
Subject: RE: Molalla Ave. cross-section
Hi Jenn,
Hope you had a merry Christmas.
As requested, we ran the numbers for the full depth section (curb to curb) 200 ft on either side of the Main Street intersection. We estimate that the additional cost will be approximately $20K. If there is potential that the parking lanes will be used for turn lanes in the near future, it does seem prudent to consider this as part of the current project. Let us know and we can update the typical section and estimate.
As requested we have included language in the special provisions to require a static roller on the cement treated subgrade.
Also, as you suggested, we have removed the cross sections from the plan set to reduce the number a sheets. We will add a note that the cross section grades will be available from the Engineer during construction.
Thanks!
Chris Link, P.E. | Civil Engineer, Associate
Licensed in OR, WA
T: 541.741.2975 | Cell: 503.869.4885 | Chris.Link@msa-ep.com
777 High Street, Suite 200 | Eugene, Oregon 97401 | www.msa-ep.com
Murray, Smith & Associates, Inc. | Your Public Works Partner
Notice: This e-mail and any attached files are the private confidential property of the sender, and the materials are privileged communications intended solely for the receipt, use, benefit and information of the intended recipient indicated above. If you are not the intended recipient, you are hereby notified that any review, disclosure, copying, distribution, or taking of any other action in reliance on the contents of this transmission is strictly prohibited, and may result in legal liability on your part. If you have received this e-mail in error, please notify us immediately at the above address.
P Please consider the environment before printing this e-mail.
From: Jennifer Cline [mailto:jcline@cityofmolalla.com]
Sent: Tuesday, December 22, 2015 9:44 AM
To: Chris Link <Chris.Link@msa-ep.com>
Cc: Hash, Kenneth F. <HashK@hdjdg.com>
Subject: Molalla Ave. cross-section
Hi Chris,
I would like to see what the additional cost would be to build full depth (curb to curb) 200 ft on either side of the Main Street intersection, beginning at the proposed sawcut line.
Also, do we have something (note, standard or special) that says only to static roll the cement amended soil.
Thank you,
Jennifer Cline, P.E. | Public Works Director
Licensed in OR, WA
117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038
O: 503.759.0218 | F: 503.829.3676