From: Jennifer Cline

Sent: Wed Sep 03 16:55:30 2014

To: Dan Huff

Subject: FW: Invoice

Importance: Normal

 

I don’t know the history here…

From: Cherie Spahn [mailto:cheriespahn@gmail.com]

Sent: Wednesday, September 03, 2014 4:43 PM

To: Jennifer Cline

Subject: Re: Invoice

Hello Jennifer,

The way we calculated the invoice was taking the total invoice of $24,700 divided by 16 lots times 5 lots that were already built on.

$24,700 / 16= $1,543.75 x 5 lots= $7,718.75.

I believe that the $7,265.00 amount was calculated on a lower bid.

If you take $7,265 / 5= $1,453 per lot x 16 lots= $24,688.00

The difference is $1,452.00 / 16= $90.75 x 5 lots= $453.75

Let me know if this makes any sense to you.

You can call or email me to go over the amounts.

Thank You,

 

Cherie Spahn

CFO

Chad E. Davis Construction, LLC

2420 Pacific Ave

Forest Grove, OR 97116

503-357-8587 (Office)

503-992-2301 (Fax)

503-709-1659 (Cell)

cheriespahn@gmail.com

On Wed, Sep 3, 2014 at 4:19 PM, Jennifer Cline <jcline@cityofmolalla.com> wrote:

Hi Cherie,

Thank you for providing the attached invoice. Will you please provide an explanation for additional $453.75 invoiced. This invoice is more than the city’s agreed portion of $7265.00. Please see attached signed agreement.

Regards,

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.829.6855 Ext. #218

F: 503.829.3676