From: Jennifer Cline

Sent: Thu Dec 18 16:45:33 2014

To: Dan Huff

Cc: Garrett Edmunds; Heather Penni

Subject: FW: CS15A457 City Of Molalla new pump service.pdf

Importance: Normal

Attachments: image001.jpg; CS15A457 City Of Molalla new pump service.pdf;

 

Hi Dan,

Here is the estimate for the power/service work at the S. Molalla pump. The estimate includes two cost (1) Installing a new utility pole (2) Utilizing the existing utility pole. This work is in addition to the pump connection and starters installed today to the existing PGE service system. Hopefully we do not need to use a new pole.

Jennifer Cline, P.E.

City of Molalla

Public Works Director

O: 503.759.0218

F: 503.829.3676

image "file:///C:

From: Tony Carson [mailto:tcarson@cherrycityelectric.com]

Sent: Thursday, December 18, 2014 1:32 PM

To: Jennifer Cline (jcline@cityofmolalla.com)

Subject: CS15A457 City Of Molalla new pump service.pdf

Hi Jennifer,

Here’s the pricing for the new pump service we just talked about. Both options are listed.

Let me know if you need anything else. Thank you

Sincerely,

Tony Carson

Service Project Manager/Estimator

Cherry City Electric

Phone: 503-566-5600 (24 Hour Service)

Direct: 503-566-5576

Fax: 503-362-2468

Cell: 503-983-2407

Web Page: http://www.CherryCityElectric.com

Video Link: www.impactmovie.com/cce

image