From: Jennifer Cline

Sent: Thu Apr 07 12:01:26 2016

To: Gerald Fisher

Subject: FW: Approved Stone Place Ph. 3 - Public Improvement Plans

Importance: Normal

Attachments: 20160407070246.pdf;

 

These item costs look a little low to me. i.e. C900 8” is $40/ft for the Molalla Ave project and they were significantly lower than 21 other bids. Even without prevailing wage, $13/ft is less than 1/2

Can you make edits if you have private developer unit costs. I don’t have access to those.

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676

From: Jeff Bolton [mailto:JBolton@mtengineering.net]

Sent: Thursday, April 07, 2016 7:22 AM

To: 'Jennifer Cline' <jcline@cityofmolalla.com>

Subject: RE: Approved Stone Place Ph. 3 - Public Improvement Plans

Jennifer,

Based upon the final public plans, I have updated the engineer estimate for both sanitary and the fire line as requested.

They are both attached.

Jeff

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Wednesday, April 06, 2016 11:54 AM

To: Jeff Bolton

Cc: Nicolas Lennartz

Subject: RE: Approved Stone Place Ph. 3 - Public Improvement Plans

Certainly. Please send an updated construction cost estimate of all the public improvements; including but not limited to the fire hydrant line and sanitary sewer.

Thanks,

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676

From: Jeff Bolton [mailto:JBolton@mtengineering.net]

Sent: Wednesday, April 06, 2016 8:56 AM

To: 'Jennifer Cline' <jcline@cityofmolalla.com>

Subject: RE: Approved Stone Place Ph. 3 - Public Improvement Plans

Jennifer,

You are correct on the timing for the public permits, I just get pressure from Karl Ivanov’s Lender – Key Bank on permit status.

Would it be possible that you could have the permits fees determined during the week of April 18th?

Thanks,

Jeff Bolton

Multi/Tech Engineering

(503) 363-9227

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Tuesday, April 05, 2016 10:33 AM

To: Jeff Bolton

Subject: RE: Approved Stone Place Ph. 3 - Public Improvement Plans

Haven’t touched them, I have had a few days off.

You’re last email indicated you were not planning to do any public improvement work anytime soon. Has the schedule changed?

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676

From: Jeff Bolton [mailto:JBolton@mtengineering.net]

Sent: Tuesday, April 05, 2016 10:13 AM

To: 'Jennifer Cline' <jcline@cityofmolalla.com>

Subject: RE: Approved Stone Place Ph. 3 - Public Improvement Plans

Jennifer,

How are you doing on the permits for the Public Construction? I am needing to update the Lender (Key Bank) on the status of public permits,

Thanks,

Jeff Bolton

From: Jennifer Cline [mailto:jcline@cityofmolalla.com]

Sent: Wednesday, March 30, 2016 3:54 PM

To: Jeff Bolton

Cc: Nicolas Lennartz; Dan Huff; 'Gerald Fisher'; Dennis Welle; 'Karin Irish'

Subject: Approved Stone Place Ph. 3 - Public Improvement Plans

Hi Jeff,

Attached are the approved final public improvement plans for Stone Place Ph. 3. Please note, no work may begin without a construction permit. I will work on preparing that, along with the cost estimate for you.

Please let me know if there are any questions.

Regards,

Jennifer Cline, P.E. | Public Works Director

Licensed in OR, WA

City of Molalla

117 N Molalla Ave. | PO Box 248 * |Molalla, OR 97038

O: 503.759.0218 | F: 503.829.3676

image