From: Jennifer Cline
Sent: Fri Mar 13 09:44:40 2015
To: Nicolas Lennartz
Subject: FW: 4 Corners Map
Importance: Normal
Attachments: 4 corners map.pdf; FYI – for the possible developer. Jennifer Cline, P.E. City of Molalla Public Works Director O: 503.759.0218 F: 503.829.3676 From: Dan Zinder [mailto:dzinder@cityofmolalla.com] Sent: Friday, March 13, 2015 9:39 AM To: Jennifer Cline Subject: 4 Corners Map Hi Jenn, Here’s a map showing City Utilities for the 4 Corners area. I did some collection out there this week and then traced in the rest from the plans. Notes: - The plans show 8” PVC sewer line in the 211/213 intersection bumping west a bit and then heading up 213. I asked Roy about it and he said they weren’t able to build that part because they ran into the 24” force main. I’m not sure if it does this and won’t until we can do collection out there. - Also of note, I didn’t include the force main in this map but should he develop we can get him that, as well. Best, - - - - - - - - - Dan Zinder GIS Analyst City of Molalla 503.759.0226 503.586.8094 (c)