From: Jennifer Cline
Sent: Wed Sep 24 16:16:44 2014
To: 'Jim'
Cc: Dan Huff; Garrett Edmunds
Subject: Alyssa Meadows Paving
Importance: Normal
Attachments: Smelser Checks.pdf; AlyssyMeadowsSmelserLetter.pdf; Hi Jim, Attached is the copy of the checks we are holding from Steve Smelser totaling $20,454.60. The city’s responsibility is $23,181.88 as noted in the attached letter. If we cannot collect the remaining $1,363.64 from Carlos Flores, the City will cover that portion as we have done before. I know time is running short with the weather, when would you like to plan the work? It appears after next week we may have some clear weather. Regards, Jennifer Cline, P.E. City of Molalla Public Works Director O: 503.829.6855 Ext. #218 F: 503.829.3676