Attachments: image001.jpg; 10_October 2023 O& M Field Report.pdf; 11_November 2023 O& M Field Report.pdf; 12_December 2023 O& M Field Report.pdf; 20231012 Monthly O& M Field Notes.pdf; 20231116 Monthly O& M Field Notes.pdf; 20231213 Monthly O& M Field Notes.pdf; ALS Labs_2330303-Report.pdf; Pace Labs_L1666709-Report.pdf;

 

 

You don't often get email from shill@farallonconsulting.com. Learn why this is important

 

 
 

Hi Mark,

Attached are the unzipped files. Please confirm receipt. Thank you!

image

 

Soren Hill

Project Compliance Specialist

Farallon Consulting

Phone 503-880-6230

From: PUGH Mark * DEQ <mark.pugh@deq.oregon.gov>

Sent: Tuesday, January 16, 2024 1:21 PM

To: Soren Hill <shill@farallonconsulting.com>

Cc: Andie Fitzgerald <afitzgerald@terwilligerplaza.com>; Chuck Esler <cesler@farallonconsulting.com>; Tanya Battye <tbattye@farallonconsulting.com>

Subject: RE: Former 5 Star Cleaners - Q4 Progress Report

Soren, I am unable to open the field or analytical report files.

From: Soren Hill <shill@farallonconsulting.com>

Sent: Monday, January 15, 2024 3:51 PM

To: PUGH Mark * DEQ <mark.pugh@deq.oregon.gov>

Cc: Andie Fitzgerald <afitzgerald@terwilligerplaza.com>; Chuck Esler <cesler@farallonconsulting.com>; Tanya Battye <tbattye@farallonconsulting.com>

Subject: Former 5 Star Cleaners - Q4 Progress Report

Mark,

This email provides a quarterly progress report for the former Five Star Cleaners property at 2305 SW 6th Avenue (DEQ ECSI Site ID No. 6276). This progress report is being submitted for the fourth quarter of 2023, on behalf of Pacific Skyline Holdings II, LLC.

Actions taken during the previous 3 months:

 

o Concentrations of volatile organic compounds (VOCs) were measured using a hand-held photoionization detector (PID) at select monitoring points including at the vapor collection system, sub-slab vapor pins, and vapor recovery wells. PID readings are summarized in Table 1 (attached).

o Differential pressures were measured at the subslab vapor points (VP-5 through VP-8) using a hand-held vacuum gauge. Differential pressure readings are summarized in the O&M field reports.

· Semi-annual air samples were collected from the influent (pre-carbon) and effluent (post-carbon) lines of the vapor granular activated carbon treatment vessels using summa canisters on October 12, 2023. The samples were submitted to Pace Analytical laboratories for analysis using U.S. Environmental Protection Agency (EPA) Method TO-15 for VOCs including but not limited to tetrachloroethene (PCE) and trichloroethene (TCE). Analytical results for the vapor collection system are shown in Table 2 (attached). The analytical report is also attached.

· Indoor and outdoor ambient air samples were collected using Radiello badges between October 12 and October 26, 2023. The samples were submitted to ALS Laboratories for analysis for PCE and TCE by EPA Method TO-17. Ambient air analytical results are shown in Table 3 (Attached). The analytical report is also attached.

· The Vapor Collection System Operations and Maintenance (O&M) Manual was revised with updated contact information, minor text edits providing clarity to field staff, and a redundant system checklist was added to the monthly inspection form. The revised O&M Manual (revised October 20, 2023) was submitted to DEQ via email on October 25, 2023.

Summary of sampling, test results, and any other data generated or received during the previous 3 months:

Monthly O&M field reports are attached. PID readings are tabulated in Table 1 (attached).

Pre- and post-carbon and indoor and outdoor air sampling analytical results from the October 2023 sampling event are presented in Tables 2 and 3, respectively. Those results are summarized as follows:

 

A description of any problems experienced during the previous three months and actions taken to resolve them:

 

Actions scheduled in the next 3 months:

 

If DEQ has questions about the information provided in this progress report, please do not hesitate to contact us.

Thank you,