From: Gerald Fisher
Sent: Wed Oct 24 15:43:25 2018
To: Andy Peters
Subject: RE: Compliance Checklists (RWUP and MAO)
Importance: Normal
Is the Piezometer section supposed to say that they read more than 1 ft?
Regards,
Gerald Fisher, P.E. | Public Works Director
City of Molalla
117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038
Office: 503.829.6855 | Direct: 503.759.0218
CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.
From: Andy Peters
Sent: Wednesday, October 17, 2018 12:52 PM
To: Gerald Fisher <gfisher@cityofmolalla.com>; Jake Ehredt <jehredt@cityofmolalla.com>; Jaimee Searcy <jsearcy@cityofmolalla.com>; James Clifton <jclifton@cityofmolalla.com>
Subject: Compliance Checklists (RWUP and MAO)
Okay the MAO checklist is now done too, I’ve gone ahead and issued both as SOP#48 in the Controlled Documents folder. Feel free to review and provide feedback. These Meta-checklists need not contain all the data or readings, they just need to ensure we are DOING the readings and using them properly in decision making. Let me know if I’ve left anything out, nothing is set in stone and I’m totally open to better ideas.
Otherwise, these can go into effect over the next few weeks.
We will add the Consent Decree checklist when it’s signed, and rev-inc the SOP.
Thanks!
Andy Peters
City of Molalla
Public Works Operations Supervisor
(503) 829-6855 x220
Cell: 503-793-0507
117 N Molalla Ave
Molalla, OR 97038