From: Gerald Fisher
Sent: Tue Aug 29 16:31:54 2017
To: Jason Clifford; Dan Huff
Subject: RE: barscreen rebuild
Importance: Normal
Thanks Jason. Will this cause you any issues with the aeration basin and stuff getting through or are we OK?
Regards,
Gerald Fisher, P.E. | Public Works Director
City of Molalla
117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038
Office: 503.829.6855 | Direct: 503.759.0218
CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.
From: Jason Clifford [mailto:jclifford@cityofmolalla.com]
Sent: Tuesday, August 29, 2017 1:12 PM
To: Gerald Fisher <gfisher@cityofmolalla.com>; Dan Huff <dhuff@cityofmolalla.com>
Subject: barscreen rebuild
Dan, Gerald,
(2) techs will be here 9/11 to rebuild the screen. It will probably take 5-6 days.
Thanks,
Jason