Regular cost to do a digout assuming large quantities is approximately $35-$40 per square yard. That puts the small quantities at $94 per square yard (2.5 times) which is not unreasonable. Good work Andy.

Regards,

Gerald Fisher, P.E. | Public Works Director

City of Molalla

117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038

Office: 503.829.6855 | Direct: 503.759.0218

CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.

From: Andy Peters <apeters@cityofmolalla.com>

Sent: Thursday, October 1, 2020 10:49 AM

To: Gerald Fisher <gfisher@cityofmolalla.com>; Dan Huff <dhuff@cityofmolalla.com>

Subject: PO 3992

Gerald/Dan, just an accounting cleanup thing: when we had Newman Paving come do the aprons on Industrial Way we originally asked for a PO to do 575 sf. We ended up excavating and replacing 1092.24 sf, so the final bill was $11,385. That’s only $10.43 per sf for the Industrial Roadway section (with our guys doing the dig-out and base rock). I was guessing it was going to be $11 per sf, so I think we still got a good deal. In any case, I am going to increase the amount of the PO to Match, which means the system will send it to Dan for after-the-fact signature.