From: Gerald Fisher
Sent: Wed Feb 20 16:30:02 2019
To: Rozzell, Matthew
Subject: RE: Right of way permit
Importance: Normal
Attachments: image001.png; image004.png; image005.gif; Thanks Matt. I told them to get the braces off my right of way and internal to the building. They know they have to get approvals from you folks. The company is Cascade NW Construction and they may be requesting an expedite on any permits they may need. Regards, Gerald Fisher, P.E. | Public Works Director City of Molalla 117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038 Office: 503.829.6855 | Direct: 503.759.0218 CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you. From: Rozzell, Matthew <MRozzell@co.clackamas.or.us> Sent: Wednesday, February 20, 2019 3:29 PM To: Gerald Fisher <gfisher@cityofmolalla.com> Subject: FW: Right of way permit Hi Gerald, Here is Andy’s analysis. Let me know if you have any questions. Thanks, -Matt From: Anderson, Andy Sent: Wednesday, February 20, 2019 2:43 PM To: Rozzell, Matthew <MRozzell@co.clackamas.or.us> Subject: RE: Right of way permit Hi, I ran analysis for the pipe and anchors for the exterior and interior conditions. For exterior condition I assumed the brace was only in compression and the anchors are only seeing shear forces. For the interior condition I assumed the brace could be in compression or tension and worst case for the anchors is tension and shear. The Simpson Titen HD 5/8”x6” anchors require a minimum embedment of 4.5 inches, and a minimum 6” concrete thickness. For the exterior condition the anchor connection to the sidewalk is 1% over capacity. For the interior condition the anchorage capacity is exceeded by a factor of 2. None of these loads have been factored by omega. Regards, Andy A. Anderson, P.E. | Structural Review Engineer Clackamas County Department of Transportation and Development | Building Codes Division 150 Beavercreek Rd | Oregon City, OR 97045 aanderson2@clackamas.us | 503-742-4783 (Office) From: Rozzell, Matthew <MRozzell@co.clackamas.or.us> Sent: Tuesday, February 19, 2019 8:23 AM To: Anderson, Andy <AAnderson2@co.clackamas.or.us> Subject: FW: Right of way permit Hi Andy, This is the building that burned a few weeks ago in Molalla. Can you take a look at the bracing they put up for the front wall and talk after. Thanks, -Matt From: Gerald Fisher [mailto:gfisher@cityofmolalla.com] Sent: Friday, February 15, 2019 2:06 PM To: Rozzell, Matthew <MRozzell@co.clackamas.or.us> Subject: RE: Right of way permit Here are images of the work for structural review. Thanks. Regards, Gerald Fisher, P.E. | Public Works Director City of Molalla 117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038 Office: 503.829.6855 | Direct: 503.759.0218 CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you. From: Gerald Fisher Sent: Friday, February 15, 2019 1:51 PM To: 'mrozzell@clackamas.us' <mrozzell@clackamas.us> Subject: FW: Right of way permit Hi Matt, The building across the street from City Hall recently burned and today a contractor set braces on the front of the building without any permits. He stated their intent is to clear out debris on the inside of the structure so that they can set the braces on the inside and then remove the ones on the front of the building. Since this is a building permit related issue, I cant issue a temporary right of way permit without at least having someone from the building side of things look at it and send me something that says the bracing is OK. Can you have someone in your office contact me on Tuesday so we can assist the property owner with protecting the right of way and their structure. I will be in the office all day on Tuesday. Thanks Matt. Regards, Gerald Fisher, P.E. | Public Works Director City of Molalla 117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038 Office: 503.829.6855 | Direct: 503.759.0218 CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you. From: Seth P <Sethp@cascadenwconstruction.com> Sent: Friday, February 15, 2019 1:28 PM To: Gerald Fisher <gfisher@cityofmolalla.com> Cc: Michelle M <Michellem@cascadenwconstruction.com>; Andy McBride <AndyM@cascadenwconstruction.com> Subject: Right of way permit Hello Gerald- Is this what you are looking for? If you think you need more or specific information let me know. Thank you, Project Manager Cascade NW Construction sethp@cascadenwconstruction.com 801 E. Main St. Molalla, OR 97038 | O: 503.919.2201 | C: 971.272.4925 OR CCB #201730 | WA #CASCANC821BR | OEC 408 COMMUNICATION Seth Pownall