From: Gerald Fisher

Sent: Thu Mar 26 14:42:40 2020

To: Andy Peters

Subject: RE: 316 Berkley

Importance: Normal

Attachments: image001.jpg;

 

That was a point of I&I so we will bill to I&I for the replacement.

Regards,

Gerald Fisher, P.E. | Public Works Director

City of Molalla

117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038

Office: 503.829.6855 | Direct: 503.759.0218

CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.

From: Andy Peters <apeters@cityofmolalla.com>

Sent: Thursday, March 26, 2020 12:59 PM

To: Gerald Fisher <gfisher@cityofmolalla.com>

Subject: RE: 316 Berkley

Roger. I’m going to get it flowing today and then plate it, I don’t have enough 6” pipe on hand to finish, and starting the job now would leave our guys working OT till about 8pm. Will plan this out and hit it next week.

That cheapo camera we bought a few years ago served us well but now it’s dying! I’m glad we budgeted for one next year!

Andy

From: Gerald Fisher <gfisher@cityofmolalla.com>

Sent: Thursday, March 26, 2020 12:56 PM

To: Andy Peters <apeters@cityofmolalla.com>

Subject: RE: 316 Berkley

Yes, that is a violation of the health code. I bet they broke the lateral when installing the waterline and did a patch and buried it. We need to reinstall the sewer service line deeper. Here is the crossing detail. Need 18” between pipes. Depth at manhole to flowline at south is 7.69 feet and to north is 6.10 so there is plenty of depth to come out of the main and run 2% then bring up behind cleanout.

Regards,

Gerald Fisher, P.E. | Public Works Director

City of Molalla

117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038

Office: 503.829.6855 | Direct: 503.759.0218

CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.

From: Andy Peters <apeters@cityofmolalla.com>

Sent: Thursday, March 26, 2020 12:21 PM

To: Gerald Fisher <gfisher@cityofmolalla.com>

Subject: Berkely

Gerald, a picture for you. 8" water main layed directly over 6" sewer lateral, the root cause of the crushed pipe on Berkely. This is why we are having to reimburse the property owner that $995. So sad.

Andy

image

Andy