Gerald as you know we are finished with the Open Cleanout smoke tests and are moving on to the next I/I issues. Dan Zinder reviewed Dyer’s flow poking report and pulled all the videos available. From that he identified all the point sources that we can easily dig up and repair. There are Seven jobs, and we’ve launched all of them on the schedule below. We don’t think this will be expensive, but I’ve included it in the budget I gave you yesterday in case we find we need to contract one or two of them. The videos are reports are attached to each work order, visible on the Utility_Crew Load Report.
We are letting you know so you have and Ace when speaking with Engineers and Lawyers and Politicians this spring. I/I is still our priority as we try to reduce flows before it’s time to size the new plant.
Andy
Isolated Repairs Recommended
TL_A2_2 –TL_A2_5 – E 7th ST
TL_B_5 - TL_B_2 – Patrol ST
TL_A1_4 –EOL CO – E 8th ST
TL_B_20 –TL_B_21 – Fenton Ave
TL_A1_6 –EOL CO – E 8th ST
BC_A3_2 –EOL CO: – Metzler Ave NOTE: Wrong MH #s on report but this is the correct report
BC_A3_10 –BC_A3_17 – Sweigle Ave
Andy Peters