From: Susan Hansen
Sent: Wed Jul 26 13:15:35 2017
To: DECONCINI Nina
Subject: RE: Response to Molalla yet?
Importance: Normal
Why is it taking so long to answer the simple question below - if there are any new written emails or MAOs or letters, etc. I will as usual need to file a PIR. So please update me - you said last week nothing had gone on, you should know whether or not anything has transpired. Susan
> -----Original Message-----
> From: nina.deconcini@state.or.us
> Sent: Wed, 26 Jul 2017 19:57:38 +0000
> To: foxglovefarm@inbox.com
> Subject: RE: Response to Molalla yet?
>
> Susan,
>
> We are in the process of responding to both this email and your public
> records request.
>
> Nina
>
>
>
> Sent from my Verizon Wireless 4G LTE smartphone
>
>
> -------- Original message --------
> From: Susan Hansen <foxglovefarm@inbox.com>
> Date: 7/26/17 11:23 (GMT-08:00)
> To: Susan Hansen <foxglovefarm@inbox.com>, DECONCINI Nina
> <nina.deconcini@state.or.us>
> Subject: RE: Response to Molalla yet?
>
> Dear Nina,
>
> You were able to quickly respond to my Dan email - please respond to the
> below message. My observation is that endless stalling is happening.
> Susan
>
>
> -----Original Message-----
> From: foxglovefarm@inbox.com
> Sent: Wed, 26 Jul 2017 06:48:36 -0800
> To: nina.deconcini@state.or.us
> Subject: Response to Molalla yet?
>
> Dear Ms. Deconcini,
>
> Has any correspondence - letters, emails, PENS, etc about the wastewater
> issues in Molalla occurred between DEQ staff and the City of Molalla/
> Ring Bender since the July 5 meeting? Have any meetings occurred - if so
> when? Has DEQ updated its draft MAO? The DEQ draft MAO failed to reflect
> the 24 days of Class One discharge violations into the Molalla River in
> May/ June 2017. Thanks for providing transparency on your process.
>
> Also, how much time does DEQ allow to pass in fruitless negotiations
> before it acts on the growing number of serious violations, most noted in
> the draft MAO, less the 24 days of Class One discharge violations in May/
> June. It is now going on TEN MONTHS since the Class One discharge
> violations in October (resulting in a PEN) and about six month overdue
> for a plan to test ground water to see if the lagoons are leaking. Does
> DEQ intend to allow the stalling to go on forever and to allow the
> violations to continue to occur?
>
> Sincerely,
> Susan Hansen
> Bear Creek Recovery
>
>
>
> -----Original Message-----
> From: nina.deconcini@state.or.us
> Sent: Wed, 19 Jul 2017 15:16:01 +0000
> To: foxglovefarm@inbox.com
> Subject: RE: Response to Molalla yet?
>
>
> We are in discussions about setting up a time to meet about the MAO. With
> everyone’s schedules, it is taking some time. I don’t know exactly when
> it will occur, but we are working on it. There has been no
> communication in written form shared since the July 5th meeting.
>
>
>
> From: Susan Hansen [mailto:foxglovefarm@inbox.com]
> Sent: Wednesday, July 19, 2017 8:10 AM
> To: DECONCINI Nina <nina.deconcini@state.or.us>
> Subject: RE: Response to Molalla yet?
>
>
>
> So when you say "discussions" how is that accomplished - via email? On
> the phone? Again, the notes I read said prompt response, what kind of
> response are you planning and has ANY COMMUNICATION IN WRITTEN FORM
> happened since the July 5 meeting? Susan
>
>
>
>
>
> -----Original Message-----
> From: nina.deconcini@state.or.us<mailto:nina.deconcini@state.or.us>
> Sent: Wed, 19 Jul 2017 14:48:32 +0000
> To: foxglovefarm@inbox.com<mailto:foxglovefarm@inbox.com>
> Subject: RE: Response to Molalla yet?
>
> Susan,
>
>
>
> We are still in the process of the MAO discussions with the City. We
> have not sent any response.
>
>
>
> Nina
>
>
>
> From: Susan Hansen [mailto:foxglovefarm@inbox.com]
> Sent: Tuesday, July 18, 2017 6:39 PM
> To: DECONCINI Nina
> <nina.deconcini@state.or.us<mailto:nina.deconcini@state.or.us>>
> Subject: Response to Molalla yet?
>
>
>
> Dear Nina,
>
> Did DEQ write any response yet to Molalla after the July 5 meeting and/or
> about Molalla's MAO proposal? One of the notes I obtained said DEQ need
> to make a prompt response after that July 5 meeting.
>
> Susan Hansen
> Bear Creek Recovery