From: Susan Hansen

Sent: Wed Jul 26 11:23:42 2017

To: Susan Hansen; DECONCINI Nina

Subject: RE: Response to Molalla yet?b Importance: Normal

 

Dear Nina,

 

You were able to quickly respond to my Dan email - please respond to the below message. My observation is that endless stalling is happening. Susan

 

 

 

-----Original Message-----

From: foxglovefarm@inbox.com

Sent: Wed, 26 Jul 2017 06:48:36 -0800

To: nina.deconcini@state.or.us

Subject: Response to Molalla yet?

 

Dear Ms. Deconcini,

 

Has any correspondence - letters, emails, PENS, etc about the wastewater issues in Molalla occurred between DEQ staff and the City of Molalla/ Ring Bender since the July 5 meeting? Have any meetings occurred - if so when? Has DEQ updated its draft MAO? The DEQ draft MAO failed to reflect the 24 days of Class One discharge violations into the Molalla River in May/ June 2017. Thanks for providing transparency on your process.

 

Also, how much time does DEQ allow to pass in fruitless negotiations before it acts on the growing number of serious violations, most noted in the draft MAO, less the 24 days of Class One discharge violations in May/ June. It is now going on TEN MONTHS since the Class One discharge violations in October (resulting in a PEN) and about six month overdue for a plan to test ground water to see if the lagoons are leaking. Does DEQ intend to allow the stalling to go on forever and to allow the violations to continue to occur?

 

Sincerely,

Susan Hansen

Bear Creek Recovery

 

 

 

-----Original Message-----

From: nina.deconcini@state.or.us

Sent: Wed, 19 Jul 2017 15:16:01 +0000

To: foxglovefarm@inbox.com

Subject: RE: Response to Molalla yet?

 

We are in discussions about setting up a time to meet about the MAO. With everyone’s schedules, it is taking some time. I don’t know exactly when it will occur, but we are working on it. There has been no communication in written form shared since the July 5th meeting.

From: Susan Hansen [mailto:foxglovefarm@inbox.com]

Sent: Wednesday, July 19, 2017 8:10 AM

To: DECONCINI Nina <nina.deconcini@state.or.us>

Subject: RE: Response to Molalla yet?

So when you say "discussions" how is that accomplished - via email? On the phone? Again, the notes I read said prompt response, what kind of response are you planning and has ANY COMMUNICATION IN WRITTEN FORM happened since the July 5 meeting? Susan

-----Original Message-----

From: nina.deconcini@state.or.us

Sent: Wed, 19 Jul 2017 14:48:32 +0000

To: foxglovefarm@inbox.com

Subject: RE: Response to Molalla yet?

Susan,

We are still in the process of the MAO discussions with the City. We have not sent any response.

Nina

From: Susan Hansen [mailto:foxglovefarm@inbox.com]

Sent: Tuesday, July 18, 2017 6:39 PM

To: DECONCINI Nina <nina.deconcini@state.or.us>

Subject: Response to Molalla yet?

Dear Nina,

 

Did DEQ write any response yet to Molalla after the July 5 meeting and/or about Molalla's MAO proposal? One of the notes I obtained said DEQ need to make a prompt response after that July 5 meeting.

 

Susan Hansen