Maybe in the future to avoid confusing the public the City and its engineers should start to say "proposed" or "future" or "anticipated" instead of making it appear that such things like amended plans with Class C wastewater allowed and MAOs which don't exist yet are done deals. Molalla has put out enough false spin, maybe you could gain an ounce of trust if you were more careful about how you put out your reports and notices. After years of hearing the baloney about how well the wastewater mgt. was going, it's about time you attempt to generate trust by telling the EXACT TRUTH, no matter how ugly the TRUTH is about your horrible wastewater fiasco.

 

Susan Hansen

Bear Creek Recovery

 

 

 

-----Original Message-----

From: gfisher@cityofmolalla.com

Sent: Wed, 28 Mar 2018 14:02:28 -0700 (PDT)

To: foxglovefarm@inbox.com

Subject: RE: Questions about the 16-10 WWMP - I&I Flow Mapping Report posted to the website

 

Dear Ms. Hansen,

The 2018 MAO is referenced as a placeholder in the draft copy of Section 2. (See attached page 2-1) Once the City enters into the MAO with DEQ and we have finalized Section 2, then the document will no longer be a draft. If we do not finalize the MAO with DEQ prior to completion of the master plan then we will modify or remove the language, whichever is deemed appropriate by the City and DEQ. Thank you for your question and let me know if you have any other questions regarding the documents provided on our project webpage. You can also submit questions to our project email at WWMP@cityofmolalla.com.

Regards,

Gerald Fisher, P.E. | Public Works Director

City of Molalla

117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038

Office: 503.829.6855 | Direct: 503.759.0218

CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.

From: Susan Hansen [mailto:foxglovefarm@inbox.com]

Sent: Wednesday, March 28, 2018 10:54 AM

To: Gerald Fisher <gfisher@cityofmolalla.com>

Cc: YELTON-BRAM Tiffany <tiffany.yelton-bram@state.or.us>; Richard Whitman <richard.whitman@state.or.us>; DECONCINI Nina <nina.deconcini@state.or.us>; rdavis@oregonian.com; kswigart@cityofmolalla.com; jthompson@cityofmolalla.com

Subject: Questions about the 16-10 WWMP - I&I Flow Mapping Report posted to the website

The timeline lists a 2018 MAO and refers to an appendix A with the claimed MAO. When did the City of Molalla execute a MAO with ODEQ and where is that appendix A?

 