From: YELTON-BRAM Tiffany

Sent: Fri Aug 25 17:20:52 2017

To: 'Susan Hansen'; YELTON-BRAM Tiffany; DECONCINI Nina

Subject: RE: Lagoon leak test response

Importance: Normal

 

Hello Susan

No, we have not yet done a detailed review of the leak test report. We have other permit holders with pressing enforcement issues that are taking priority. It is on the work list for one of my engineers and his higher priority work should be wrapping up by middle of next week.

Tiffany

From: Susan Hansen [mailto:foxglovefarm@inbox.com]

Sent: Thursday, August 24, 2017 1:36 PM

To: YELTON-BRAM Tiffany <tiffany.yelton-bram@state.or.us>; DECONCINI Nina <nina.deconcini@state.or.us>

Subject: Lagoon leak test response

Dear Tiffany and Nina,

 

Has DEQ responded to the new lagoon leak test yet? If so what is the response document called so I can do a request.

 

Susan Hansen

Bear Creek Recovery