From: SVETKOVICH Christine

Sent: Wed Oct 12 13:17:53 2016

To: YELTON-BRAM Tiffany; DECONCINI Nina

Subject: FW: copy of Mutual Agreement and Order

Importance: Normal

 

Just FYI on a now, closed loop.

Christine

From: SVETKOVICH Christine

Sent: Wednesday, October 12, 2016 1:17 PM

To: 'Susan Hansen'

Subject: RE: copy of Mutual Agreement and Order

HI Susan—

One of our inspectors conducted an inspection of the Molalla Redi-Mix site this morning. The site is in compliance with the industrial stormwater general permit it is covered under.

If you have additional questions about this site, please let me know.

Best—

Christine

From: Susan Hansen [mailto:foxglovefarm@inbox.com]

Sent: Wednesday, September 21, 2016 4:26 PM

To: SVETKOVICH Christine

Subject: RE: copy of Mutual Agreement and Order

Thanks so much, keep me posted when you have the information to share. Susan, Bear Creek Recovery

-----Original Message-----

From: christine.svetkovich@state.or.us

Sent: Wed, 21 Sep 2016 23:14:20 +0000

To: foxglovefarm@inbox.com

Subject: RE: copy of Mutual Agreement and Order

HI Susan—

Thank you for your inquiry below. My group is in the process of reviewing the most recent Discharge Monitoring Reports that were due at the end of July 2016, for all of the facilities registered under the 1200 Z industrial stormwater permit. This is the general permit that Molalla Redi-Mix is covered under. Once those reviews are complete, likely by mid-October, I will be able to respond to your question.

I will be in touch in October with an update. If you have any questions, let me know.

Best—

Christine

From: Susan Hansen [mailto:foxglovefarm@inbox.com]

Sent: Wednesday, September 21, 2016 10:53 AM

To: SVETKOVICH Christine

Subject: RE: copy of Mutual Agreement and Order

Hello, What is the status of Molalla Redi-Mix in terms of current compliance with DEQ permit. Thanks, Susan Hansen Bear Creek Recovery

-----Original Message-----

From: svetkovich.christine@deq.state.or.us

Sent: Wed, 27 May 2015 18:02:57 +0000

To: foxglovefarm@inbox.com

Subject: RE: copy of Mutual Agreement and Order

Susan-

Thank you for letting me know the web link below does not work. I have attached the press release and will work with our team that does the web postings to fix the link.

DEQ requires all permittees to follow the conditions of the general permits they are assigned to. Yes, DEQ reviews all of the annual reports and associated discharge monitoring reports that are submitted by permittes as required by the permits. The reviews typically take place during the fall and we follow-up up with compliance and enforcement in accordance with our guidance.

Molalla Redi-Mix does not have any additional requirements, other than those outlined in the general permit. Yes, the reason for the DEQ penalty, and ultimate enforcement action, was because the annual report was not submitted and is required as a permit condition. DEQ will monitor Redi-Mix’s compliance with monitoring requirements and other permit conditions.

If you have additional questions, please let me know.

Best-

Christine

From: Susan Hansen [mailto:foxglovefarm@inbox.com]

Sent: Tuesday, May 26, 2015 4:26 PM

To: Susan Hansen; SVETKOVICH Christine

Subject: RE: copy of Mutual Agreement and Order

Christine, I just tried again to find the notice of the Nov. 7 fine via www.oregon.gov/deq/docs/110614MolallaRedi-Mix.pdf but it comes back as error - maybe DEQ takes down the notices after awhile? That is the document I am looking for or whatever document outlines what caused the fine to be generated. Thanks again, Susan

-----Original Message-----

From: foxglovefarm@inbox.com

Sent: Tue, 26 May 2015 15:12:43 -0800

To: svetkovich.christine@deq.state.or.us

Subject: RE: copy of Mutual Agreement and Order

Thanks Christine. Could you send when you have time the document that was sent about the penalty. And will Redi-Mix have to do anything extra in terms of its testing / reporting now that it has been a violator at least twice - for failing to get its permanent permit when it finished construction and now due to this? Will DEQ more carefully monitor Redi-Mix? I saw in my email files my question to Dennis Jurries from last summer - in August 2014 Jurries assured me he was expecting Redi-Mix's report that I guess never came? Do you check to make certain all companies like this provide the proper reports each year in a timely manner. I am anxious to understand if it was one missing report that caused this fine or was it more than that? Thanks, Susan Hansen, Bear Creek Recovery

\

 

 

 

 

-----Original Message-----

From: svetkovich.christine@deq.state.or.us

Sent: Tue, 26 May 2015 23:03:27 +0000

To: foxglovefarm@inbox.com

Subject: copy of Mutual Agreement and Order

HI Susan- As promised, attached is the document we discussed. If you have questions, please let me know.

Best-