From: Dan Huff

Sent: Tue Oct 27 11:53:49 2020

To: Mac Corthell

Cc: Gerald Fisher

Subject: RE: Timeline of Events - Dollar General

Importance: Normal

Attachments: image001.jpg;

 

When was the official pre-application conference?

From: Mac Corthell <mcorthell@cityofmolalla.com>

Sent: Tuesday, October 27, 2020 10:40 AM

To: Dan Huff <dhuff@cityofmolalla.com>; Gerald Fisher <gfisher@cityofmolalla.com>

Subject: RE: Timeline of Events - Dollar General

Gerald,

My responses are in red below. Can you fill out the highlighted section and let me know if you see any inaccuracies in my responses. I don’t have the benefit of having been party to all of this. The questions stem from the timeline we provided (attached).

-Mac

Macahan “Mac” Corthell, J.D. | Planning Director

City of Molalla

117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038

Phone - 503.829.6855

Fax – 503.829.3676

Email – mcorthell@cityofmolalla.com

Website – http://www.cityofmolalla.com

CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.

From: Dan Huff <dhuff@cityofmolalla.com>

Sent: Tuesday, October 27, 2020 10:25 AM

To: Mac Corthell <mcorthell@cityofmolalla.com>

Subject: FW: Timeline of Events - Dollar General

Mac – Can you answer her questions? Just forward the answers to me and I will send to her. I will let you be the night in shinning armor with this thing at some point.

From: Leota Childress <lchildress@cityofmolalla.com>

Sent: Tuesday, October 27, 2020 10:19 AM

To: Dan Huff <dhuff@cityofmolalla.com>

Subject: Re: Timeline of Events - Dollar General

I think it looks good. Just a few questions, clarifications.

SDR = Sight Design Review?

Correct.

NOD = Notice of Decision?

Correct.

If we are going to disseminate this, it might be good to spell them out the first time they're used.

Will do.

Are there any notes or documentation about when $ Gen was told the SDCs were going up?

Did $ Gen have to wait until March 2020 to submit building permit application due to complications with Cascade Center?

Not to submit. Their SDR approval was final 8/19/20, they could have submitted any time after that.

At what exact point in the process are SDCs calculated and firm?

Once a building permit is received and deemed “complete” under the law, the application is forwarded internally for comment and Public Works calculates SDC’s as part of their comment.

Do we, at this time, have everything needed to issue a building permit?

No, we’re still waiting on their third attempt at a complete application due to lack of a light plan and expanded civic space in front of the building.

As an aside, we cannot issue the building permit until the Final Plat is recorded with Clackamas County. But, even if the final plat had been recorded, we could not issue due to lack of the items mentioned above.

What I'm trying to get at here is whether or not $ Gen is even ready to build.

No. They need to submit the light plan and civic space expansion; and cascade center needs to finish recording their final plat.

Leota Childress

City Council President

City of Molalla

503.829.6855


 

From: Dan Huff

Sent: Tuesday, October 27, 2020 8:16:58 AM

To: Leota Childress

Subject: Timeline of Events - Dollar General

Let me know what you think of this timeline for Dollar General.

Dan Huff

City Manager

City of Molalla, Oregon

(503)829-6855

image

______________________________________________________________________________

PUBLIC RECORDS LAW DISCLOSURE

This e-mail is a public record of the City of Molalla and is subject to public disclosure unless exempt from disclosure under Oregon Public Records Law. This e-mail is subject to State Retention Schedule.