We received the contractors schedule for top lift of paving this morning. It is as follows:
· Thursday – Post no parking signs for sweeping on Friday
· Friday – Sweep and prep for paving. Restore Parking
· Saturday – no work
· Sunday – Post no parking signs for paving on Monday, Tuesday, and Wednesday
· Monday – Top lift paving
· Tuesday – Top lift paving. Restore parking if possible.
· Wednesday – Top lift paving if needed. Restore parking.
· Striping no earlier than April 11th or 12th based on paving completion and weather dependent.
Feel free to share on your website and with your members.
Regards,
Gerald Fisher, P.E. | Public Works Director
City of Molalla
117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038
Office: 503.829.6855 | Direct: 503.759.0218
CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.