Dan,
Feel free to share with Council.
Sanitary, storm, water, and streetlighting underground will be done by next Tuesday. Tuesday reconstruction of the roadway begins and will continue thru the week. Substantial complete so far is November 28th and final completion is December 13th. These were the original contract dates. The contractor is pushing to finish ahead of schedule if possible. Thanks.
Regards,
Gerald Fisher, P.E. | Public Works Director
City of Molalla
117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038
Office: 503.829.6855 | Direct: 503.759.0218
CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.