From: Gerald Fisher
Sent: Thu Feb 02 17:04:30 2017
To: Dan Huff
Subject: PW Project List for Council
Importance: Normal
Hi Dan,
The following is a list of ongoing Public Works projects and status: Winter = Jan – Mar, Spring = Apr – Jun, Summer = Jul – Sep, Fall = Oct - Dec
Public Projects
15-02 2017 Waterline Improvements (Metzler, 3rd, 4th, and Faurie) – Construction summer and fall of 2017
15-05 City Hall Parking Lot Improvements – Complete fall of 2017
15-06 Water Right Certification – Complete fall of 2017
15-07 City Hall Remodel Ph. 1 – Complete spring of 2017
15-10 SDC Methodology Update – Completed December 2016
15-11 WWTP Lagoon Leak Test – Completed December 2016
16-01 Molalla Ave UR Project – Complete spring of 2017
16-04 City Hall Parking Lot Storm – Completed January 2017
16-05 Clark Park Partition – Complete summer of 2017
16-07 PW Shop Facility Improvements – Complete winter of 2018
16-08 Lola Ave Sewer Improvements – Complete fall of 2018
16-10 Wastewater Master Plan Update – Complete summer of 2018
16-11 Transportation Master Plan Update – Complete summer of 2018
16-12 Molalla Code Update – Complete summer of 2017
16-13 WWTP O&M Manual Update – Complete spring of 2017
16-14 Bear Creek Byway – Complete spring of 2017
16-15 I&I Project – Complete spring of 2018
16-16 OR 211 Ped Improvements (213 to Ona) – Complete summer of 2019
17-02 2017 Rate Study – Complete summer of 2017
WTP Capital Improvement List – Complete spring of 2017
WWTP Capital Improvement List – Complete spring of 2017
WWTP Storm Drainage Repairs – Complete summer 2018
Public Works Standards Update – Complete winter of 2018
TMDL Implementation Plan – Complete winter of 2018
WWTP Monitoring Wells – Complete spring of 2018
Private Projects
16-02 Stoneplace Apartments Ph 3 – Complete summer of 2017
16-03 Rondel Court Apartments – Complete summer of 2017
16-17 Bear Creek Subdivision – Complete winter of 2018
17-01 Stow Away Storage – Complete spring of 2017
Dixon Ice Plant – Complete fall of 2017
MRM Frontage Improvements – Complete summer of 2018
Shirley Bank Subdivision – Complete fall of 2017
Twin Meadows Subdivision – Complete Winter of 2018
That’s all I can think of big picture. There’s a ton of little stuff that is fill in as time and funding allows. Thanks.
Regards,
Gerald Fisher, P.E. | Public Works Director
City of Molalla
117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038
Office: 503.829.6855 | Direct: 503.759.0218
CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.