From: Gerald Fisher
Sent: Mon Aug 22 13:56:09 2016
To: Mark Strandberg (Ring-Bender)
Cc: Dan Huff (Molalla)
Subject: FW:
Importance: Normal
FYI. Almost sounds like they are bored and looking for something to delay getting back to their office. We’ve discussed the procedure ad-nauseam and I’m not going to be interested in saying the same stuff 10 times to burn the clock.
From: Gerald Fisher [mailto:gfisher@cityofmolalla.com]
Sent: Monday, August 22, 2016 1:53 PM
To: YELTON-BRAM Tiffany <tiffany.yelton-bram@state.or.us>
Cc: Dan Huff <dhuff@cityofmolalla.com>; COLE David <david.cole@state.or.us>; BAILEY Randall <randall.bailey@state.or.us>; Ryan Quigley <rquigley@dyerpart.com>; Steve Major <smajor@dyerpart.com>
Subject: RE: Molalla WWTP Lagoon Leak Test - Meeting w/DEQ to review dry run
Hi Tiffany,
We will meet here at City Hall. Ryan will be prepared to discuss the testing with Randy at that time. Other than the testing procedure the meeting should be short. We can then go to the WWTP if necessary to go over the setup. Other than travel time to the plant, we should be able to cover everything needed in less than one hour. Not a whole lot to talk about with the process. See you tomorrow morning. Thanks.
Regards,
Gerald Fisher, P.E. | Public Works Director
City of Molalla
117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038
Office: 503.829.6855 | Direct: 503.759.0218
CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.
From: YELTON-BRAM Tiffany [mailto:tiffany.yelton-bram@state.or.us]
Sent: Monday, August 22, 2016 10:37 AM
To: COLE David <david.cole@state.or.us>; 'Gerald Fisher' <gfisher@cityofmolalla.com>; BAILEY Randall <randall.bailey@state.or.us>; Ryan Quigley <rquigley@dyerpart.com>; Steve Major <smajor@dyerpart.com>
Cc: Dan Huff <dhuff@cityofmolalla.com>
Subject: RE: Molalla WWTP Lagoon Leak Test - Meeting w/DEQ to review dry run
Hi Gerald
Randy, David and I will be at City Hall at 9am tomorrow. We’d like to go to the wastewater treatment plant to better understand the set up. Since that might take a bit, can we have a total of 1 1/2hours of your time instead of just an hour? We could simply meet at the plant which might save us all a little time. Let me know what works best for you. Thanks!
Tiffany Yelton Bram
WQ Source Control Manager
Oregon Department of Environmental Quality
700 NE Multnomah St., Suite #600
Portland OR 97232
Desk 503 229 5219
Mobile 503 975 0046
-----Original Appointment-----
From: Gerald Fisher [mailto:gfisher@cityofmolalla.com]
Sent: Tuesday, July 26, 2016 11:42 AM
To: Gerald Fisher; Ryan Quigley; Steve Major; COLE David; BAILEY Randall; YELTON-BRAM Tiffany
Cc: Dan Huff
Subject: Molalla WWTP Lagoon Leak Test - Meeting w/DEQ to review dry run
When: Tuesday, August 23, 2016 9:00 AM-10:00 AM (UTC-08:00) Pacific Time (US & Canada).
Where: Molalla City Hall