From: Steve Donovan
Sent: Fri Jan 14 11:54:23 2022
To: Andy Peters
Subject: RE: SDC Calculation
Importance: Normal
Here are my calculations:
ITE code 851 adjusted PMPHVTs 17.05 per 1,000 sf of floor area
Cost per PMPHVT $4,226
Proposed development size 4,323 sf of floor area
SDC Fee:
17.05 * $4,226 *4.323 = $311,486.42
From: Andy Peters <apeters@cityofmolalla.com>
Sent: Friday, January 14, 2022 11:44 AM
To: Steve Donovan <steve.donovan@donovan-enterprises.com>
Cc: Sam Miller <smiller@cityofmolalla.com>; Dan Zinder <dzinder@cityofmolalla.com>
Subject: SDC Calculation
Steve, Happy New Year!!
I need a simple SDC Calculation, can you help me? Obviously I’m worried that I see an issue or I wouldn’t be asking. But I’m hoping if I see the MASTER do one I will see where I’m wrong!
What is the Transportation SDC owed by this business?
Thank you!
Respectfully,
Andy Peters, Public Works Div Manager
315 Kennel Ave. | PO Box 248 |Molalla, OR 97038
Phone – 503.759.0220
Email – apeters@cityofmolalla.com
Website – http://www.cityofmolalla.com