From: Pete Sipos

Sent: Tue Dec 18 15:42:14 2018

To: Andy Peters

Cc: petesipos; Casey Bochsler

Subject: FW: Revised Kennel @ Hwy 211 RFQ

Importance: Normal

Attachments: image001.jpg; image003.jpg; image005.jpg; Request for Quotes - Kennel at Hwy211, center at hwy 211 REVISED 12-13-18.pdf;

 

Andy,

The lump sum price to perform the asphalt repair work as per the attached request for proposal is $ 31,200.00. This price is based on closing the roadway and detouring traffic for two days. Please let us know as soon as you can if we will be helping you improve your roadway system.

Thank you

Pete Sipos image

North Santiam Paving Co.

E: Petes@nspor.com

P: 503-769-3436 ext 206

F: 503-769-7358

C: 503-932-4162

W: www.NSPor.com

image

 

 
 

CONFIDENTIALITY NOTICE: Please do not read, copy, or disseminate this communication unless you are the intended addressee. This e-mail may contain confidential and/or privileged information intended only for the addressee. If you have received this in error, please notify me via return e-mail.

From: Casey Bochsler [mailto:caseyb@nspor.com]

Sent: Tuesday, December 18, 2018 2:11 PM

To: petes@nspor.com

Subject: FW: Revised Kennel @ Hwy 211 RFQ

Casey Bochsler image

North Santiam Paving Co.

E: caseyb@nspor.com

P: 503-769-3436

F: 503-769-7358

C: 503-932-1282

W: www.NSPor.com

 

 
 

CONFIDENTIALITY NOTICE: Please do not read, copy, or disseminate this communication unless you are the intended addressee. This e-mail may contain confidential and/or privileged information intended only for the addressee. If you have received this in error, please notify me via return e-mail.

From: Andy Peters [mailto:apeters@cityofmolalla.com]

Sent: Thursday, December 13, 2018 4:18 PM

To: Andy Peters

Cc: Megan Verdoorn - Contractor Plan Center; Jake Eagle; grady@gtexcavating.com; Casey Bochsler

Subject: Revised Kennel @ Hwy 211 RFQ

Please find attached a REVISED VERSION of the RFQ for diggouts here in Molalla. Just one strikethrough: we’ll use the standard ½” HMAC mix, instead of the ¾”, since it’s what folks are using these days.

Thanks,

Andy Peters

City of Molalla

Public Works Operations Supervisor

(503) 829-6855 x220

Cell: 503-793-0507

apeters@cityofmolalla.com

117 N Molalla Ave

Molalla, OR 97038