From: Chaunee Seifried

Sent: Wed Sep 16 11:22:54 2020

To: Gerald Fisher

Cc: Dan Huff

Subject: Re: 4594 Patrol Street Sewer & Water MEI NOD-001 Wildfire Evacuation & Smoke Impacts

Importance: Normal

Attachments: image001.jpg;

 

Yes... we will need a good trail to report things to fema.

Thanks,

Chaunee

 

Sent from my iPhone

 

On Sep 16, 2020, at 10:27 AM, Gerald Fisher <gfisher@cityofmolalla.com> wrote:

 



If there is a cost impact on our project that is not covered under the “not responsible for things out of our control” then we will need to claim that amount with FEMA. Will keep track of it as we go forward.

Regards,

Gerald Fisher, P.E. | Public Works Director

City of Molalla

117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038

Office: 503.829.6855 | Direct: 503.759.0218

CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.

From: Patrick Bachmeier <Patrick.Bachmeier@themeigroup.com>

Sent: Wednesday, September 16, 2020 10:16 AM

To: C Heuberger <cheuberger@dyerpart.com>

Cc: Gerald Fisher <gfisher@cityofmolalla.com>; George Wells <George.Wells@themeigroup.com>

Subject: 4594 Patrol Street Sewer & Water MEI NOD-001 Wildfire Evacuation & Smoke Impacts

Cody,

Attached is our formal Notice of Delay regarding the ongoing wildfires. Please let us know if you have questions or need any further information.

Thank you,

PATRICK BACHMEIER, LEED AP

Project Manager / Estimator

C 971-865-0200 | o 503-674-0900 | f 503-674-0959

www.themeigroup.com

PO Box 798, 5501 NE 223rd Ave. Fairview, OR 97024

<image001.jpg>

<4594 PSS&W_MEI NOD-001.pdf>