From: YELTON-BRAM Tiffany
Sent: Fri Oct 31 16:47:19 2014
To: 'Jennifer Cline'
Cc: Phillip Bender
Subject: FW: Molalla issues
Importance: Normal
Attachments: RE: RE: I and I report for Molalla; Molalla-Final-Permit.pdf; Hello Jennifer I wanted to remind you of the due date for the Inflow Removal Plan as described in the city’s NPDES permit. I would appreciate an update on this next week. I would still like to have a meeting with you and our permit writer, David Cole, to walk through the permit. Nina Deconcini, our regional administrator would also like to attend. David and I could go out your office and bring Nina in by phone. Would 10am on Wednesday, November 19th work for you? Thanks! Tiffany Yelton Bram Water Quality Source Control Section Manager Water Quality Program, NW Region Oregon Department of Environmental Quality 2020 SW 4th Ave., Suite 150 Portland OR 97201-4987 desk 503 229 5219 mobile 503 975 0046 From: YELTON-BRAM Tiffany Sent: Friday, October 31, 2014 4:39 PM To: 'Susan Hansen' Cc: DECONCINI Nina; HAMMOND Joni Subject: RE: Molalla issues Hello Susan Regarding the Inflow Removal Plan, the City has a 180 days from the issuance of their permit to create this plan. The permit was issued 5/12/2014 and so the city has to November 11, 2014 to provide the plan. I spoke on the phone with Jennifer Cline, the new public works director, on October 8th (we could not work out a September 30th meeting) and one of the items we discussed was the progress on creating this plan. The city is working on this but was not yet ready to share a draft. As of right now, no compliance dates related to Infiltration and Inflow have been missed. I have attached the e-mail that you quoted from, Susan, and a copy of the permit for reference. Tiffany Yelton Bram Water Quality Source Control Section Manager Water Quality Program, NW Region Oregon Department of Environmental Quality 2020 SW 4th Ave., Suite 150 Portland OR 97201-4987 desk 503 229 5219 mobile 503 975 0046 From: Susan Hansen [mailto:foxglovefarm@inbox.com] Sent: Thursday, October 30, 2014 2:02 PM To: YELTON-BRAM Tiffany Cc: DECONCINI Nina; HAMMOND Joni Subject: Molalla issues Dear Tiffany, In reviewing email exchanges we had since early Sept. I have a couple of questions. First, I asked for EPA contacts who oversee the work of Oregon DEQ in relation to wastewater programs for cities like Molalla. You have not provided that info. Second, you indicated you would be following up with Molalla about the progress of their I&I: "During the Spring and Summer of 2014, I had meetings with the city where they stated that a more comprehensive I& I study to determine the overall status of the collection system and associated infrastructure would be created. Section 1 of Schedule D in the NPDES permit issued to Molalla sets a clear requirement that within 180 days of issuing the permit, the city would submit for approval an Inflow Removal Plan. This plan then becomes the benchmark by which annual progress will be measured. I will be following up with the city on Tuesday, September 30th, about the progress on this plan." Did you follow up on Sept 30 and what is the progress? Thanks, Susan Hansen Bear Creek Recovery