From: DeHart, Kyle

Sent: Fri Jan 17 13:13:05 2020

To: LIVERMAN Alex; Herwig, Britta

Cc: Ryals, Cindy; SEIDEL Paul; Felice, Rachel; ELWORTH Susan

Subject: RE: Follow-up on Forest Park Warning Letter deadline

Importance: Normal

Attachments: image001.jpg;

 

Microsoft Exchange Server;converted from html;

Good afternoon Alex,

I hope this finds you well. I want to acknowledge that Britta and I have received this information and are diligently working to have our response to DEQ to by end of business on Tuesday, January 21st. Our response will be sure to include relevant information regarding the qualified contractors and the amendment of the Project Manager, from Rachel Felice to me, in line with what was discussed at our January 7th meeting. We thank you for clearly explaining the rationale and process associated with the October 31, 2020 deadline and will adhere to what you have outlined.

We will be sure to remain in contact as we develop the work plan and will request your assistance, as-needed, throughout the review and permitting process. Thank you again, and, we too are also looking forward to the day we have permanent stormwater controls in place.

Sincerely,

Kyle

Kyle DeHart (he, him, his)

Health, Safety, & Environmental Specialist | Assets & Development

Portland Parks & Recreation

6437 SE Division St.

Portland, OR 97206

(503) 502-4534 (Cell)

Kyle.DeHart@PortlandOregon.gov

portlandparks.org

 

The City of Portland complies with all non‐discrimination Civil Rights laws including Civil Rights Title VI and ADA Title II. To help ensure equal access to City programs, services and activities, the City of Portland will reasonably modify policies/procedures and provide auxiliary aids/services to persons with disabilities. Call 503-858-9744, TTY 503-823-6868 or Oregon Relay Service 711 with requests, or visit http://bit.ly/13EWaCg

image

Find us on Facebook | Twitter | YouTube | Instagram

From: LIVERMAN Alex

Sent: Wednesday, January 15, 2020 3:19 PM

To: Herwig, Britta

Cc: Ryals, Cindy ; DeHart, Kyle ; SEIDEL Paul ; Felice, Rachel ; ELWORTH Susan

Subject: Follow-up on Forest Park Warning Letter deadline

Hi Britta.

I tried calling you today to relay information you requested on DEQ’s enforcement process. I haven’t heard back from you and wanted to get this information to you, since you are working on a response following our meeting on Jan 7th. Please do respond to DEQ to meet the terms of the Order as to the qualified contractor list and amending the project manager in the Order by Jan 21st, as we agreed to at the meeting. Likely, you will want to provide a separate response on discrepancies in the letter that Rachel mentioned wanting to address, but you may include these together if you prefer.

After conferring with DEQ’s Office of Compliance and Enforcement and my manager, Paul Seidel, I also recommend that you write a separate response regarding timeline, but likely not until closer to the Oct 31 deadline. Here’s why:

 

I hope this provides the information you need to move the project forward, but please feel free to call or email me to discuss, as needed. Also, please contact me as you work on the plan or need support for reviews and permitting. I look forward to getting permanent stormwater controls on the ground and issuing a certification of completion.

--Alex

L. Alexandra Liverman

Portland Harbor Stormwater Coordinator

Oregon Department of Environmental Quality

Northwest Region Cleanup Program

700 NE Multnomah Street, Suite 600

Portland Oregon 97232-4100

503-229-5080

503-229-6945 (fax)

liverman.alex@deq.state.or.us