From: Gerald Fisher

Sent: Fri Jul 17 08:15:38 2020

To: 'Jeff Bolton'; Julie Larson; Dan Zinder

Cc: Sam Miller; Jeffrey Bivens

Subject: RE: Cascade Center Plat

Importance: Normal

Attachments: image001.png;

 

All,

Please change the Subject line when communicating about a project that is different the Cascade Center. If it is an application for the storage units east of Leroy then it needs another name. Also, Sam and I don’t need to be included on emails between the developer and Planning in the application process. Planning will forward information that needs to be reviewed by PW when the time comes. Thanks.

Regards,

Gerald Fisher, P.E. | Public Works Director

City of Molalla

117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038

Office: 503.829.6855 | Direct: 503.759.0218

CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.

From: Jeff Bolton <JBolton@mtengineering.net>

Sent: Thursday, July 16, 2020 12:39 PM

To: Julie Larson <jlarson@cityofmolalla.com>; Dan Zinder <dzinder@cityofmolalla.com>

Cc: Gerald Fisher <gfisher@cityofmolalla.com>; Sam Miller <smiller@cityofmolalla.com>; Jeffrey Bivens <jeffb@iecon.us>

Subject: RE: Cascade Center Plat

Hey Julie,

The application was resubmitted on Tuesday, July 7th. This is one day before the July 8th date per the deemed incomplete letter.

Mr. Zinder had contacted our office that he would like the resubmittal package in chronological order which I have done on a disk.

This was per his request by email.

 

Jeff

From: Julie Larson <jlarson@cityofmolalla.com>

Sent: Thursday, July 16, 2020 12:17 PM

To: Jeff Bolton <JBolton@mtengineering.net>; Dan Zinder <dzinder@cityofmolalla.com>

Cc: Gerald Fisher <gfisher@cityofmolalla.com>; Sam Miller <smiller@cityofmolalla.com>; Jeffrey Bivens <jeffb@iecon.us>

Subject: RE: Cascade Center Plat

Hi Jeff-

Is this for the Phase II Project? If so, the 180 day time period has lapsed since the 1st application was submitted. The fee to submit the Site Design Review is $3000.00

Thanks,

Julie Larson

City of Molalla | Planning Specialist

117 N Molalla Ave. | Molalla, OR 97038

Direct: 503-759-0243 | Office: 503-829-6855

Business Hours: M-F 8:30-4:30

image

From: Jeff Bolton <JBolton@mtengineering.net>

Sent: Thursday, July 16, 2020 11:14 AM

To: Dan Zinder <dzinder@cityofmolalla.com>

Cc: Gerald Fisher <gfisher@cityofmolalla.com>; Sam Miller <smiller@cityofmolalla.com>; Jeffrey Bivens <jeffb@iecon.us>; Julie Larson <jlarson@cityofmolalla.com>

Subject: RE: Cascade Center Plat

Good morning Dan,

Per our conversation on Monday afternoon, I will be by your office later this afternoon.

On disk I will have the submittal package on disk for you to download as requested.

Guessing that I will be there around 3:45 to 4:00 PM.

Jeff Bolton

Multi/Tech Engineering

(503) 363-9227

From: Dan Zinder <dzinder@cityofmolalla.com>

Sent: Monday, July 13, 2020 2:09 PM

To: Jeff Bolton <JBolton@mtengineering.net>

Cc: Gerald Fisher <gfisher@cityofmolalla.com>; Sam Miller <smiller@cityofmolalla.com>; Jeffrey Bivens <jeffb@iecon.us>; Julie Larson <jlarson@cityofmolalla.com>

Subject: RE: Cascade Center Plat

Hi Jeff,

Thanks for the heads up.

FYI, final plat review fee is $300. The City is of course waiting upon ODOT approvals for processing this application.

Also, your office submitted drawings that I presume were for the Phase II Application that was submitted last fall/winter. The submission came in the form of several emails with individually attached pages. This application will need to be submitted as one complete package for our review.

Best,

Dan Zinder

503.759.0226

From: Jeff Bolton <JBolton@mtengineering.net>

Sent: Monday, July 13, 2020 2:00 PM

To: Dan Zinder <dzinder@cityofmolalla.com>

Cc: Gerald Fisher <gfisher@cityofmolalla.com>; Sam Miller <smiller@cityofmolalla.com>

Subject: Cascade Center Plat

Good afternoon Dan,

Our office resubmitted the public civil construction plans for Cascade Center back on July 2, 2020. Based upon the updated construction plans our survey staff have also updated the Plat for this project.

The Plat now includes updated easement for the public sanitary sewer location, public water/fire hydrant easement locations and accessways.

I realize that Public Works will need complete their review of the updated construction plans, but also wanted to have the final updated Plat at your office. I plan on stopping by your office later this afternoon (3:45 PM) and will include a check for $ 200.00 to cover the City plat review fee. The Plat is also copied to a Disk.

Just wanted to give you a heads up.

Jeff Bolton

Multi/Tech Engineering

(503) 363-9227