From: Gerald Fisher

Sent: Tue Feb 07 17:56:15 2017

To: Gary Darling

Subject: RE: Shirley Bank Subdivision

Importance: Normal

 

Hi Gary,

We have to be able to clean the detention pipe and vactor out sediment. We also have a high groundwater table in this area. I am familiar with the open bottom version of stormtech but not a closed system that can withstand the jetter. If you can supply me with something to review, I will consider it. Thanks and have a good evening.

Regards,

Gerald Fisher, P.E. | Public Works Director

City of Molalla

117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038

Office: 503.829.6855 | Direct: 503.759.0218

CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.

From: Gary Darling [mailto:gid@dleng.net]

Sent: Monday, February 06, 2017 3:02 PM

To: 'Gerald Fisher' <gfisher@cityofmolalla.com>

Subject: RE: Shirley Bank Subdivision

Hi Gerald,

I am working on the construction documents – I am also aware of the upcoming hearing.

But I had a question about the detention. We are proposing below ground detention (not in the public right of way)

Will the city allow Stormtech chambers or is large pipe preferred for detention?

Gary

From: Gerald Fisher [mailto:gfisher@cityofmolalla.com]

Sent: Friday, February 3, 2017 12:30 PM

To: Tim Tkachenko <tt@dleng.net>

Cc: Gary Darling <gid@dleng.net>

Subject: RE: Shirley Bank Subdivision

Here is the contact info I have. You will only need water down through gas. Thanks.

Regards,

Gerald Fisher, P.E. | Public Works Director

City of Molalla

117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038

Office: 503.829.6855 | Direct: 503.759.0218

CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.

From: Tim Tkachenko [mailto:tt@dleng.net]

Sent: Friday, February 03, 2017 10:21 AM

To: 'Gerald Fisher' <gfisher@cityofmolalla.com>

Cc: 'Gary Darling' <gid@dleng.net>

Subject: RE: Shirley Bank Subdivision

Thanks Gerald.

Do you by any chance have the private utility names and contacts affiliated with this project?

Tim Tkachenko

Utility Coordinator

DL Design Group Inc

500 W 8th St Suite 205

Vancouver WA 98660

(503) 644-4628

From: Gerald Fisher [mailto:gfisher@cityofmolalla.com]

Sent: Thursday, February 2, 2017 2:36 PM

To: Tim Tkachenko <tt@dleng.net>

Cc: Gary Darling <gid@dleng.net>

Subject: RE: Shirley Bank Subdivision

Hi Tim,

Here is the link to our PW standards http://www.cityofmolalla.com/publicworks/page/design-standards and the link to our PW Construction Permit Application http://www.cityofmolalla.com/publicworks/page/public-works-permits. The DEQ permit will likely go to Portland but you may want call them to confirm.

Also, the subdivision is being appealed by ODOT and we will have to wait until that is resolved through our City Council at the February 8th meeting. Once that is done and we know if anything changed in the conditions of approval we will be able to accept plan submittals. Thanks and let me know if you have any questions.

Regards,

Gerald Fisher, P.E. | Public Works Director

City of Molalla

117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038

Office: 503.829.6855 | Direct: 503.759.0218

CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.

From: Tim Tkachenko [mailto:tt@dleng.net]

Sent: Thursday, February 02, 2017 2:12 PM

To: dpw@cityofmolalla.com

Cc: 'Gary Darling' <gid@dleng.net>

Subject: Shirley Bank Subdivision

Hi Gerald,

I have a couple questions regarding the project listed below.

File No.: P45-2016

Address: 14999 S HWY 211

Legal Description: Township 5 South, Range 2 East, Section 09 DA, Tax Lot 0200

Proposal: 7-lot Subdivision

We want to submit construction documents. Can you give us the requirements for that submittal?

Also, what office at DEQ do we submit the 1200C to?

Please let me know when you have the chance.

Thank you,

Tim Tkachenko

Utility Coordinator

DL Design Group Inc

500 W 8th St Suite 205

Vancouver WA 98660

(503) 644-4628


 

image

 