Thanks for the clarification Gerald, I’ll let my client know.
Steve Kay, AICP
Cascadia Planning + Development Services
503-804-1089
From: Gerald Fisher [mailto:gfisher@cityofmolalla.com]
Sent: Thursday, September 1, 2016 9:54 AM
To: Steve Kay
Cc: Dan Huff (Molalla)
Subject: RE: Shirley Bank Subdivision
Hi Steve,
Page 65 of the budget has our current CIP. There are no plans in the next 5 years or sooner to improve that roadway. The prior public works directors discussion regarding the Nazarene church had to do with full improvements at that intersection and completion of sidewalks along Shirley and Hwy 211 from Shirley southwest. That was a discussion about intersection widening and striping that would happen sometime in the future “if” the church came in with a development proposal but still does not affect or have impact to your development. Please convey to Stafford Development that they will be required to make frontage improvements along Hwy 211 along their project and that we are open to providing them with transportation SDC credits to complete the road and sidewalk to connect into the existing sidewalk on the north side of Shirley. Thanks.
Regards,
Gerald Fisher, P.E. | Public Works Director
City of Molalla
117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038
Office: 503.829.6855 | Direct: 503.759.0218
CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.
From: Steve Kay [mailto:steve@cascadiapd.com]
Sent: Thursday, September 01, 2016 8:21 AM
To: 'Gerald Fisher' <gfisher@cityofmolalla.com>
Cc: 'Dan Huff (Molalla)' <dhuff@cityofmolalla.com>
Subject: RE: Shirley Bank Subdivision
I appreciate the feedback Gerald. For clarification when updating the applicant, I believe Jennifer mentioned at the Pre-Ap that the City has a current CIP line item to install sidewalks on Hwy. 211, including frontage along the Molalla Church of the Nazarene and the Shirley Street intersection. The applicant’s proposal to provide a fee-in-lieu was based on this information and the assumption that including frontage improvements to our site as part of this larger public project would be beneficial from a public safety standpoint. Could you let me know if we misinterpreted Jennifer’s project description? If not, could you me know if this planned project changes the City’s position on granting the fee-in-lieu request?
Thanks,
Steve Kay, AICP
Cascadia Planning + Development Services
503-804-1089
From: Gerald Fisher [mailto:gfisher@cityofmolalla.com]
Sent: Wednesday, August 31, 2016 4:02 PM
To: Steve Kay
Cc: Dan Huff (Molalla)
Subject: RE: Shirley Bank Subdivision
Hi Steve,
I spoke with Dan and we are not aware of any improvement by ODOT in that area. They may have a paving or chip seal project scheduled but would not widen and improve the roadway to include bike lanes and sidewalks. That is part of the conditions the City would apply to a new development to bring the entire frontage up to City standards in accordance with the TSP and PW standards. 19.04.210(C) is a mechanism Cities use when a planned roadway project is fronting a proposed development and is scheduled in the near future under their capital improvement plan. It allows the City, as an option, to have the developer pay a fee in lieu of improvements to cover their fair share of the frontage costs and the City will in turn use those funds in their project to make the improvements along the development frontage. We do not have a roadway widening project scheduled for this section of roadway so this provision of the code would not apply. We will require the improvements and the sidewalk ends can transition using an asphalt ramp approved by ODOT.
One of the things we could consider is and extension of the sidewalk and pavement improvement around the corner to connect in with Shirley St and the City would credit the developer on their Transportation SDC’s at the time home permits are taken out. We can do that as part of the Planning Commission process or by a development agreement. Planning Commission involves the least amount of paperwork and can be done during the design and construction process. Please let your client know if that is something they would be interested in and we can recommend that to the Planning Commission for approval. Thanks.
Regards,
Gerald Fisher, P.E. | Public Works Director
City of Molalla
117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038
Office: 503.829.6855 | Direct: 503.759.0218
CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.
From: Steve Kay [mailto:steve@cascadiapd.com]
Sent: Wednesday, August 31, 2016 2:05 PM
To: Gerald Fisher <gfisher@cityofmolalla.com>
Subject: Re: Shirley Bank Subdivision
Hi Gerald,
In my narrative, I addressed the reasons why we are requesting a deferral of the improvements under Section 18.16.020(O). The City,s mechanism for collecting a fee-in-lieu can be found under 19.04.210(C).
Besides the safety issues with a partial street improvement, it is reasonable to defer improvements on Hwy. 211 since a widening project is already planned for the area. By having the developer pay a fee-in-lieu, the City makes sure future homeowners aren't burdened by the frontage improvement costs. Let me know if you think this approach makes sense to you.
Thanks,
Steve Kay, AICP
Cascadia Planning + Development Services
On Aug 31, 2016, at 1:25 PM, Gerald Fisher <gfisher@cityofmolalla.com> wrote:
Hi Steve,
The frontage improvements are required by us and ODOT. We discussed in the pre-app that they would have to be done. Not sure where the fee in lieu came from. Only fee in lieu that I am aware of in the code has to do with Parks once you hit the pocket park threshold.
Regards,
Gerald Fisher, P.E. | Public Works Director
City of Molalla
117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038
Office: 503.829.6855 | Direct: 503.759.0218
CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.
From: Steve Kay [mailto:steve@cascadiapd.com]
Sent: Tuesday, August 30, 2016 4:28 PM
To: Gerald Fisher <gfisher@cityofmolalla.com>
Subject: FW: Shirley Bank Subdivision
Hi Gerald,
In Dan’s staff report, he states that fee-in-lieu procedures for Hwy. 211 improvements will be determined by Public Works and ODOT staff. I did not see a reference to this in your conditions of approval. Can you clarify this item for me?
Thanks,
Steve Kay, AICP
Cascadia Planning + Development Services
503-804-1089
From: Dan Huff [mailto:dhuff@cityofmolalla.com]
Sent: Tuesday, August 30, 2016 2:05 PM
Subject: RE: Shirley Bank Subdivision
Steve – I attached the Staff Report and PW Conditions of Approval. I did not attach applicant information.
Dan Huff
City Manager
City of Molalla, Oregon
(503) 829-6855
_______________________________________________________________________________
PUBLIC RECORDS LAW DISCLOSURE
This e-mail is a public record of the City of Molalla and is subject to public disclosure unless exempt from disclosure under Oregon Public Records Law. This e-mail is subject to State Retention Schedule
From: Gerald Fisher [mailto:gfisher@cityofmolalla.com]
Sent: Tuesday, August 30, 2016 10:23 AM
To: Dan Huff <dhuff@cityofmolalla.com>
Subject: Fwd: Shirley Bank Subdivision
FYI
Sent from my Verizon 4G LTE smartphone
-------- Original message --------
From: Steve Kay <steve@cascadiapd.com>
Date: 8/30/16 9:06 AM (GMT-08:00)
To: Gerald Fisher <gfisher@cityofmolalla.com>
Subject: Shirley Bank Subdivision