From: Sam Miller
Sent: Wed Aug 31 08:04:56 2022
To: 'Afanasy Piatkoff'
Subject: RE: Water meters for Eckerd St Duplexes
Importance: Normal
Good Morning Afanasy,
Before meters can be set, the meter boxes need to be installed per detail (flush to grade). I drove by yesterday and seen the southern one is still sitting on the dirt mound. Schedule an inspection once meter boxes are installed per detail, and I will reinspect and approve for meter install.
Regards,
Sam Miller | Sr. Engineer Tech.
City of Molalla
315 Kennel Ave. | PO Box 248 | Molalla, OR 97038
T : 503-759-0217 | E: smiller@cityofmolalla.com
From: Afanasy Piatkoff <frameworksap@gmail.com>
Sent: Tuesday, August 30, 2022 9:17 PM
To: Sam Miller <smiller@cityofmolalla.com>
Subject: Water meters for Eckerd St Duplexes
Hi Sam, checking on the meters.. I told the plumbers they would be installed by today per our conversation. They were planning on coming out and finishing up tomorrow. Please let me know the status of getting them installed.
Thank You
--
Afanasy Piatkoff
Frameworks Construction, Inc.
P: 503-991-0147
F: 503-982-4551