From: Dan Zinder
Sent: Mon Jan 03 16:44:44 2022
To: Afanasy Piatkoff
Cc: Sam Miller; Julie Larson; Andy Peters
Subject: Authorization review is ready for pickup.
Importance: Normal
Attachments: 20211223 - BP37-2021 Duplex SDC Calculation.pdf; 20211223 - BP38-2021 Duplex SDC Calculation.pdf; Hi Afanasy, The City has finished its authorization review for your projects. I’ve attached the estimate for a 1” meter serving two units. If you were to drop it to a 3/4” meter for each unit, each unit would run roughly $24,000 ($48,000 per duplex). Let us know which option you want and we can provide you the correct numbers for pickup. Best, Dan Zinder Senior Planner, City of Molalla 117 N Molalla Ave | PO Box 248 Direct: 503.759.0226 | Office: 503.829.6855