From: Dan Zinder
Sent: Thu Sep 24 16:00:05 2020
To: Gerald Fisher; Spencer Parsons; Dan Huff
Subject: RE: Molalla Property Line Adjustment
Importance: Normal
Attachments: image001.png; Additionally, I don’t see any indication that Stafford is intending to submit the requested documentation from item 2, numbers C, D, and E from the incompleteness letter:
Best,
Dan Zinder
503.759.0226
From: Gerald Fisher <gfisher@cityofmolalla.com>
Sent: Thursday, September 24, 2020 3:54 PM
To: Spencer Parsons <spencer@gov-law.com>; Dan Huff <dhuff@cityofmolalla.com>
Cc: Dan Zinder <dzinder@cityofmolalla.com>
Subject: RE: Molalla Property Line Adjustment
Spencer,
Just left you a message. The materials that Stafford sent are garbage and don’t match their partition or the Miller partition to the south so the roadway right of ways are never going to match. They are continuing to waste our time with garbage documents and I think it is time that we say enough is enough and drop the hammer on them. If they submit one more thing to us then it better be perfect. Absolutely perfect.
Regards,
Gerald Fisher, P.E. | Public Works Director
City of Molalla
117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038
Office: 503.829.6855 | Direct: 503.759.0218
CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.
From: Gerald Fisher
Sent: Wednesday, September 23, 2020 9:59 AM
To: Dan Zinder <dzinder@cityofmolalla.com>
Subject: RE: Molalla Property Line Adjustment
Dan,
The east ROW line for the extension of Ona will align with the east ROW line for south Ona Way on the south side of Hwy 211. They need to make that change.
Regards,
Gerald Fisher, P.E. | Public Works Director
City of Molalla
117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038
Office: 503.829.6855 | Direct: 503.759.0218
CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.
From: Dan Zinder <dzinder@cityofmolalla.com>
Sent: Tuesday, September 22, 2020 4:07 PM
To: Gerald Fisher <gfisher@cityofmolalla.com>
Subject: FW: Molalla Property Line Adjustment
FYI
Dan Zinder
503.759.0226
From: Spencer Vetter <spencer@staffordlandcompany.com>
Sent: Monday, September 21, 2020 4:43 PM
To: Dan Zinder <dzinder@cityofmolalla.com>
Cc: Spencer Parsons <spencer@gov-law.com>; Bryan Cavaness <bryan@staffordlandcompany.com>
Subject: Molalla Property Line Adjustment
Good afternoon Dan,
We are working diligently to get all the requested materials to you. Attached is the updated site plan with the corrections you requested in the letter of incompletion. The location of S Ona Way has been included, but it is an approximation based on other surveys.
The one outstanding item we have is the legal descriptions. I spoke with the surveyor earlier today. He is working on getting the legal descriptions written and should have them delivered tomorrow.
Thanks,
Spencer Vetter | Development Assistant
8840 SW Holly Lane, Wilsonville, OR 97070
spencer@staffordlandcompany.com