From: Alice Cannon

Sent: Tue Apr 14 16:29:48 2020

To: Spencer Parsons

Cc: Gerald Fisher; Penunuri@molallfire.org; Matt Rozzell (mrozzell@clackamas.us); Dan Huff

Subject: Bear Creek Subdivision Conditions of Approval Requiring Ona Way, References to Building Code Authority and References to Fire Code Authority

Importance: Normal

Attachments: image007.png; image008.png; image009.png; image010.png; image011.png; image003.png; image004.jpg; image005.png; image006.jpg; image012.png; image013.jpg; Ordinance 2016-02 Bear Creek Rezoning and Findings of Fact and Conditions.pdf; 1-18-1016 Roadway Phasing Plan and Street G Extension Submitted by Applicant.pdf; image016.jpg; image017.jpg;

 

Good afternoon Spencer:

Included in this email is the full compilation of regulatory tools that we believe Molalla Planning/PW, County Building Official and Molalla Fire Marshal can use to an use to not approve all remaining COs in Bear Creek Subdivision. Included in this email is:

  1. 1. Final Notice of Decision w/ my research highlights for your quick review. You’ll notice that this is the Ordinance approving the Zone Change. The approved Planning Commission findings and conditions for the PUD are included as an exhibit to the Zone Change Ordinance because the PUD was dependent on the Zone Change.

 

  1. 2. An infrastructure phasing plan submitted by the applicant two days before (dated 1/18/2016) the January 20, 2016 Planning Commission hearing approving the PUD. This phasing plan is referenced in the Notice of Decision.

 

  1. 3. MMC sections with enabling legislating, adopting the State Fire Code. We have also included the applicable sections of State Fire Code, requiring two access points or fire sprinklers for all developments exceeding 30 dwelling units.

 

  1. 4. MMC sections with enabling legislation, adopting the State Building Code. We have also included the applicable sections of State Building Code, enabling the Building Official to withhold COs for developments that pose a threat to health and safety.

 

It would be best if I had a chance to review these materials with you by phone and then jointly discuss next steps with you. We will want to bring Matt Rozzell and Mike Penunuri into the conversation after we have walked through these materials.

I will give you a call now to see about setting a time.

Regards,

Alice Cannon

From: Alice Cannon

Sent: Monday, April 13, 2020 2:19 PM

To: Spencer Parsons <spencer@gov-law.com>; penunuri@molallafire.org

Cc: Matt Rozzell (mrozzell@clackamas.us) <mrozzell@clackamas.us>

Subject: Bear Creek Subdivision: FIRE CODE authority in the Molalla Municipal Code ..

image

image

image

image

image

image

From: Rozzell, Matthew <MRozzell@clackamas.us>

Sent: Monday, April 13, 2020 4:34 PM

To: Alice Cannon <acannon@cityofmolalla.com>; Spencer Parsons <spencer@gov-law.com>; Gerald Fisher <gfisher@cityofmolalla.com>

Cc: Fire Dist Molalla Mike Penunuri <penunuri@molallafire.org>

Subject: RE: Bear Creek Subdivision: BUILDING CODE authority in the Molalla Municipal Code ... and empowering provisions from Chapter 1 of the 2014 Oregon Structural Specialty Code

Hi Alice,

Here are the code sections from the residential code as well as the OAR.

Thanks,

-Matt

image

image

image

From: Alice Cannon [mailto:acannon@cityofmolalla.com]

Sent: Monday, April 13, 2020 2:05 PM

To: Spencer Parsons <spencer@gov-law.com>; Rozzell, Matthew <MRozzell@clackamas.us>; Gerald Fisher <gfisher@cityofmolalla.com>

Cc: Fire Dist Molalla Mike Penunuri <penunuri@molallafire.org>

Subject: Bear Creek Subdivision: BUILDING CODE authority in the Molalla Municipal Code ... and empowering provisions from Chapter 1 of the 2014 Oregon Structural Specialty Code