From: Gerald Fisher
Sent: Thu Sep 07 10:27:03 2017
To: Brenda Reiner
Subject: RE: P27-2016 917 Toliver Road - Status of improvements
Importance: Normal
No revisions. It has been slow but in process. I told him he needs to build the east driveway and sidewalk first followed by the west driveway. He has a bond to complete the work so I am not worried about the timeline. Thanks.
Regards,
Gerald Fisher, P.E. | Public Works Director
City of Molalla
117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038
Office: 503.829.6855 | Direct: 503.759.0218
CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.
-----Original Message-----
From: Brenda Reiner [mailto:breiner@cityofmolalla.com]
Sent: Thursday, September 07, 2017 8:59 AM
To: Gerald Fisher <gfisher@cityofmolalla.com>
Subject: FW: P27-2016 917 Toliver Road - Status of improvements
Gerald,
I spoke with Peter this morning about his improvements along Toliver. He said that he just got his plat recorded with CC and he hasn't submitted a site plan to Aldo yet. He mentioned that he spoke with you about 2 phases for construction and you told him to submit his plan. He said his wife dropped it off but I haven't seen anything. The conditions of approval were written in April of 2016 so I wasn't sure if we need to redo them since it's been over a year and a half?
He said he wants to build everything within the next two months but hasn't submitted to Aldo yet.
Brenda Reiner | Senior Engineering Technician
City of Molalla
117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038
Office: 503.759.0243 I Fax: 503.829.3676
-----Original Message-----
From: Gerald Fisher [mailto:gfisher@cityofmolalla.com]
Sent: Thursday, January 19, 2017 6:36 PM
To: 'Peter Burkoff' <pbsilverfalls@live.com>
Cc: Brenda Reiner (Molalla) <breiner@cityofmolalla.com>; Aldo Rodriguez
(Molalla) <arodriguez@cityofmolalla.com>
Subject: P27-2016 917 Toliver Road - Status of improvements
Hi Peter,
I am checking on the status of improvements along Toliver Road. We have not received a permit for the improvements yet. Please coordinate with Brenda Reiner, Senior Engineering Technician with an anticipated schedule for completion of the improvements. Also, Aldo Rodriguez is our new Community Planner and he will be able to process approvals for you related to your partition and home construction. Thanks and have a good week.
Regards,
Gerald Fisher, P.E. | Public Works Director City of Molalla
117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038
Office: 503.829.6855 | Direct: 503.759.0218
CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended
recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.