From: Brenda Reiner

Sent: Tue Dec 12 10:28:02 2017

To: Peter Burkoff

Cc: Gerald Fisher

Subject: RE: Utilities/Side walk permits

Importance: Normal

 

Peter,

Three or four concrete panels are out of compliance with the maximum allowed cross slope of 2%, on your recent driveway and sidewalk pour. Please consider this written notice to remove and replace. Please call for an inspection when the forms are set.

Thanks,

Brenda Reiner | Senior Engineering Technician

City of Molalla

117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038

Office: 503.759.0243 I Fax: 503.829.3676

From: Brenda Reiner [mailto:breiner@cityofmolalla.com]

Sent: Thursday, September 07, 2017 10:47 AM

To: Peter Burkoff <pbsilverfalls@live.com>

Subject: FW: Utilities/Side walk permits

Peter,

I got ahold of your plan from Gerald. We are OK with this plan as long as you pour the other driveway as soon as the phase 1 driveway is ready for traffic. We still need you to submit for a right of way permit.

Brenda Reiner | Senior Engineering Technician

City of Molalla

117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038

Office: 503.759.0243 I Fax: 503.829.3676

From: Peter Burkoff [mailto:pbsilverfalls@live.com]

Sent: Thursday, September 07, 2017 8:02 AM

To: Gerald Fisher <gfisher@cityofmolalla.com>

Subject: Utilities/Side walk permits

Good Morning!

Gerald, I have attached document showing that I would like to start phase 1 with the sidewalk. Once utilities are ran I would like to finish phase 2 and complete the other side of the side walk. Can you provide information on how to go about pulling permit for the sidewalk and any information on pulling permit with running utilities.

Thanks,

Peter Burkoff

917 Toliver Rd

Molalla, OR 97038

pbsilverfalls@live.com

503.930.2087