From: Sam Miller

Sent: Tue Dec 10 16:55:53 2019

To: 'Cody Spanfellner'

Subject: RE: PW62-2019 747 Rachel Ln ROW Permit

Importance: Normal

 

Hi Cody,

A work order has been placed for the water meter hookup and should only take a day or two. Let me know when you have some free time to meet out on site to go over any question you might have.

Regards,

Sam Miller | Sr. Engineer Tech.

City of Molalla

117 N Molalla Ave. | PO Box 248 | Molalla, OR 97038

T : 503-759-0217 | E: smiller@cityofmolalla.com

From: Cody Spanfellner <codybuilds@gmail.com>

Sent: Tuesday, December 10, 2019 4:07 PM

To: Sam Miller <smiller@cityofmolalla.com>

Subject: Re: PW62-2019 747 Rachel Ln ROW Permit

Hi Sam,

I can't get this taken care of right away but will have it done in the next month or so. I'd like to meet you there to go over a couple things before I start digging.

Thanks, Cody

On Fri, Dec 6, 2019 at 5:03 PM Sam Miller <smiller@cityofmolalla.com> wrote:

Hello Cody.

Please see attach ROW Permit for your records. As per our discussion on the sewer clean out for the city. It is a mandatory requirement. The required width for the side walk is 5’ in that part of the subdivision development. The Placement for the clean out is behind the sidewalk and make you sure there is plenty of room for the RT cover. I have also attach the standards on residential driveway. Please let me know if you have question or concern on the standards or scheduling for inspections.

Regards,

Sam Miller | Sr. Engineer Tech.

City of Molalla

117 N Molalla Ave. | PO Box 248 | Molalla, OR 97038

T : 503-759-0217 | E: smiller@cityofmolalla.com

 

 

--

Cody Spanfellner

Owner, CJS Builders Co.

503-539-0509