From: Brenda Reiner

Sent: Mon Apr 10 11:58:52 2017

To: RAY BELL

Subject: RE: 713 e main street

Importance: Normal

 

Please disreguard – this is for testing from main to FH. For your project this won’t be needed.

Brenda Reiner

Senior Engineering Technician

City of Molalla

117 N Molalla Ave.

Direct: 503-759-0243

Office: 503-829-6855

From: RAY BELL [mailto:bellsconstruction@msn.com]

Sent: Monday, April 10, 2017 11:37 AM

To: Brenda Reiner <breiner@cityofmolalla.com>

Subject: Re: 713 e main street

i'm not familiar with this. is this from main tap to meter testing? or once line is run to residence?


 

From: Brenda Reiner <breiner@cityofmolalla.com>

Sent: Wednesday, April 5, 2017 3:53:50 PM

To: RAY BELL

Cc: handh20@juno.com

Subject: RE: 713 e main street

Attached is the City of Molallas waterline testing process. It takes about 4 days if all goes well.

Day 1 – pressure test & chlorination (50 ppm)

Day 2 – measure residual chlorination (10 ppm) and flush (must wait 48 hrs after this)

Day 3 – wait

Day 4 – take bacteria sample and take to lab

Brenda Reiner

Senior Engineering Technician

City of Molalla

117 N Molalla Ave.

Direct: 503-759-0243

Office: 503-829-6855

From: RAY BELL [mailto:bellsconstruction@msn.com]

Sent: Tuesday, March 21, 2017 2:58 PM

To: Brenda Reiner <breiner@cityofmolalla.com>

Subject: 713 e main street

checking on the site plan approval for this project. the younger gentleman (don't remember his name) was going to wrap it up and get it over to me but i haven't seen anything from him. can you follow up on this and get back to me. ray 503-313-9228