From: Brenda Reiner

Sent: Thu Jan 25 08:43:10 2018

To: Peter Burkoff

Cc: Aldo Rodriguez

Subject: RE: Plans/sidewalk

Importance: Normal

 

Peter,

I spoke with Aldo and your file is currently under planning review. This

takes about 2-3 weeks depending on the work load. Once your file is deemed

complete, then you can come in and pay your fees and SDC's.

 

 

Brenda Reiner | Senior Engineering Technician

 

City of Molalla

 

117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038

 

Office: 503.759.0243 I Fax: 503.829.3676

 

 

-----Original Message-----

From: Peter Burkoff [mailto:pbsilverfalls@live.com]

Sent: Thursday, January 25, 2018 8:38 AM

To: Brenda Reiner <breiner@cityofmolalla.com>

Subject: Re: Plans/sidewalk

 

Thanks Brenda

Your a lot easier to get a hold of then Aldo!! LOL

 

Sent from my iPhone

 

> On Jan 25, 2018, at 8:35 AM, Brenda Reiner <breiner@cityofmolalla.com>

> wrote:

>

> Peter,

> Okay, I'll check the grades.

>

>

> Brenda Reiner | Senior Engineering Technician

>

> City of Molalla

>

> 117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038

>

> Office: 503.759.0243 I Fax: 503.829.3676

>

> -----Original Message-----

> From: Peter Burkoff [mailto:pbsilverfalls@live.com]

> Sent: Thursday, January 25, 2018 8:24 AM

> To: Brenda Reiner <breiner@cityofmolalla.com>

> Subject: Re: Plans/sidewalk

>

> I think he just put a grinder to it!

>

> Sent from my iPhone

>

>> On Jan 25, 2018, at 8:13 AM, Brenda Reiner

>> <breiner@cityofmolalla.com>

>> wrote:

>>

>> Peter,

>> You need to call for inspections when you do this as I'm sure you

>> know. I will check the work but reserve the right to have you remove

>> it again since you didn't call for an inspection.

>> Thanks,

>>

>>

>> Brenda Reiner | Senior Engineering Technician

>>

>> City of Molalla

>>

>> 117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038

>>

>> Office: 503.759.0243 I Fax: 503.829.3676

>>

>> -----Original Message-----

>> From: Peter Burkoff [mailto:pbsilverfalls@live.com]

>> Sent: Wednesday, January 24, 2018 3:30 PM

>> To: breiner@cityofmolalla.com

>> Subject: Plans/sidewalk

>>

>> Hi Brenda,

>>

>> The concrete contractor corrected the sidewalk on Toliver Rd. Can you

>> look at it and sign off if it’s up to code. Also when can I

>> anticipate site plan approval so I can submit to county?

>>

>> Peter Burkoff

>>

>> Sent from my iPhone