From: Steve Smelser
Sent: Wed Dec 28 00:20:23 2016
To: Brenda Siegel
Subject: Re: 503A Kae Court PW Permit 60-2016
Importance: Normal
Thank you. I appologize. I read to call you 24 hours before an inspection, but did not read to call you when the job started. My fault. I forwarded this info to the contractor doing the work. He should be there in the morning to take care of it.
Thanks
Steve Smelser
Sent from Mailbird
On 12/27/2016 3:58:52 PM, Brenda Siegel <bsiegel@cityofmolalla.com> wrote:
Steve,
Thanks for putting cones around your rock stockpile. Additionally, please make sure that no muddy water is leaving your job site into the roadway. Please clean up the mud trail that goes from your site south into the catch basin at the corner. You need to clean up all the loose rock and mud from the roadway ASAP. I will go out there tomorrow morning and would like to see some Traffic control signage also.
Brenda Siegel
Associate Engineer
City of Molalla
503-759-0243