From: Sam Miller
Sent: Wed Jun 03 12:28:02 2020
To: 'Chas Eakman-C'
Subject: RE: 302 n Cole traffic control plan
Importance: Normal
Hello Chas,
I will need to receive a Rock Mix Design for back fill from Cody with approval before any construction can start.
Regards,
Sam Miller | Sr. Engineer Tech.
City of Molalla
117 N Molalla Ave. | PO Box 248 | Molalla, OR 97038
T : 503-759-0217 | E: smiller@cityofmolalla.com
From: Chas Eakman-C <cmosesjr@gmail.com>
Sent: Wednesday, June 3, 2020 11:52 AM
To: Sam Miller <smiller@cityofmolalla.com>
Subject: Re: 302 n Cole traffic control plan
Do you think its possible we could start tomm.?
Chas Eakman-Caldwell
Columbia Excavating inc.
503-984-5159
On Wed, Jun 3, 2020 at 9:18 AM <cmosesjr@gmail.com> wrote:
OK awesome thanks for your help
Sent from my iPhone
On Jun 3, 2020, at 8:37 AM, Sam Miller <smiller@cityofmolalla.com> wrote:
Good Morning Chas,
I will be putting the application together this morning and submitting it to Cody Spanfellner. Once approved and fees have been paid, coordinate with Cody for scheduling. Thanks.
Regards,
Sam Miller | Sr. Engineer Tech.
City of Molalla
117 N Molalla Ave. | PO Box 248 | Molalla, OR 97038
T : 503-759-0217 | E: smiller@cityofmolalla.com
From: cmosesjr@gmail.com <cmosesjr@gmail.com>
Sent: Tuesday, June 2, 2020 11:54 AM
To: Sam Miller <smiller@cityofmolalla.com>
Subject: 302 n Cole traffic control plan
Sent from my iPhone