From: Tony Brooks

Sent: Wed Sep 19 11:03:36 2018

To: Gerald Fisher; Dan Zinder; Brenda Reiner

Cc: rick.gill@molallariv.k12.or.us; Neal Lucht

Subject: Molalla Aquatic Center Utilities

Importance: Normal

Attachments: 2002-03 Molalla Aquatic Center AsBuilts.pdf; 18010A1 AQUATIC.pdf; 18010A1 AQUATIC WITH AERIAL.pdf; High School Area GIS w-aerial 02.pdf;

 

Gerald and Dan,

I believe most of the utilities were marked and we have mapped them the best we can. We mapped all the utilities features that we thought might have an impact on telling the story about existing features. We put together the attached drawing and as noted we have some questions. There are differences between what we found in the field, what GIS shows and what Aquatic Center plans noted. We need help reviewing and resolving the details.

We are also looking to know what you want for Easements?

We need limits and types of easements to call out.

Will we be grouping utilities or individual easements?

I am thinking something like a 25- or 30-foot Access and Utility Easement might cover a lot of the features from Francis Street south to just past end of pavement or something like that.

We still do not know what the configuration of the Aquatic Parcel will look like. I have not heard that a decision has been made yet. I know a lot of options were thrown around, but I did not hear any option leading the decision.

Please review and let us know your questions and comments.

Thanks,

Tony Brooks, PLS

President

Land Surveyor & GIS Tech

Ag Geospatial NW, LLC

Molalla, OR

503.329.8008 cell & text