Here are the small project conditions for this project. Also, there is an alley along the east side of this property and it does not appear to be encumbered by this garage addition from the submittals they’ve supplied.

1. Driveway and sidewalk behind driveway apron shall be constructed to current public works standards and a permit is required.

2. Rain drain connection shall be to public works standards. Recommend tying into curb at top of driveway wing.

3. Clean debris from existing sidewalk. Replace cracked and damaged sidewalk panels to current standards. Work can be covered under right of way permit.

4. This project is exempt from SDC’s.

Regards,

Gerald Fisher, P.E. | Public Works Director

City of Molalla

117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038

Office: 503.829.6855 | Direct: 503.759.0218

CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.

From: Aldo Rodriguez [mailto:arodriguez@cityofmolalla.com]

Sent: Friday, October 06, 2017 4:29 PM

To: Gerald Fisher <gfisher@cityofmolalla.com>

Cc: Brenda Reiner <breiner@cityofmolalla.com>

Subject: P57-2017 313 Sweigle Ave (New Garage)

Deemed complete 10/3/17