From: Dan Zinder
Sent: Tue May 17 09:35:18 2022
To: Mark
Cc: Sam Miller
Subject: RE: Final ?b Importance: Normal
Hi Mark,
CofO signoff is still with civil review. Each department signs off (Public Works, Planning, Finance). Let us know when you’ve paved and Planning can take a look at the house. That process should go very quickly if all matches the original plans.
Best,
Dan Zinder
503.759.0226
From: Mark <marksemail2000@gmail.com>
Sent: Monday, May 16, 2022 6:38 PM
To: Dan Zinder <dzinder@cityofmolalla.com>
Subject: Re: Final ?
Dan
Any news on Residential CofO signoff?
Thanks Mark
On Fri, May 6, 2022 at 12:25 PM Dan Zinder <dzinder@cityofmolalla.com> wrote:
Hi Mark,
I’ve attached the form your need from us. It’s a no-fee process for the first two inspections, as needed. I’d recommend dropping it by Monday as our office is a little sparse right now, myself included
Best,
Dan Zinder
503.759.0226
From: Mark <marksemail2000@gmail.com>
Sent: Wednesday, May 4, 2022 9:33 AM
To: Dan Zinder <dzinder@cityofmolalla.com>
Subject: Final ?
Good Morning Dan
We had one of our last county inspections yesterday,(130 Shirley St) and the inspector mentioned that he would need a letter from the city before he could give a final. Not sure what you need for that or how I go about obtaining it etc. (inspector was unsure what was needed other than he needed it for final).
If you could let me know I would appreciate it.
Thanks
Mark Herigstad