From: Sam Miller
Sent: Wed Apr 22 16:23:28 2020
To: 'Gerardo Herrera'
Subject: RE: 124 Berkley Ave. Row Permit
Importance: Normal
Hello Gerardo,
I need a update on the concrete brake test results. So I can move to substantial complete for this Permit. Thanks
Regards,
Sam Miller | Sr. Engineer Tech.
City of Molalla
117 N Molalla Ave. | PO Box 248 | Molalla, OR 97038
T : 503-759-0217 | E: smiller@cityofmolalla.com
From: Sam Miller
Sent: Monday, March 23, 2020 11:05 AM
To: 'Gerardo Herrera' <gsconcretework@gmail.com>
Subject: RE: 124 Berkley Ave. Row Permit
No problem, Just let me know when you are ready for a final inspection and remember to schedule for concrete testing the day of pour and you can email me the results after the 28 day braking period. Let me know if you have any question.
Thanks
Sam Miller
From: Gerardo Herrera <gsconcretework@gmail.com>
Sent: Monday, March 23, 2020 10:54 AM
To: Sam Miller <smiller@cityofmolalla.com>
Subject: Re: 124 Berkley Ave. Row Permit
Sam
Thank you so very much for all your help.
I will let you know when we will pour the new concrete.
Gerardo 'G'
On Mon, Mar 23, 2020 at 10:50 AM Sam Miller <smiller@cityofmolalla.com> wrote:
Good Morning Gerardo,
See attached file for your records. Please let me know if you have any question. Thanks.
Regards,
Sam Miller | Sr. Engineer Tech.
City of Molalla
117 N Molalla Ave. | PO Box 248 | Molalla, OR 97038
T : 503-759-0217 | E: smiller@cityofmolalla.com
From: Gerardo Herrera <gsconcretework@gmail.com>
Sent: Thursday, March 12, 2020 9:59 PM
To: Sam Miller <smiller@cityofmolalla.com>
Subject: Fwd: 124 Berkley Ave. Row Permit
Sam
Here is the mix design for the concrete mix to pour back the city sidewalk and approach from Wilsonville concrete.
Thank you
Gerardo 'G'
---------- Forwarded message ---------
From: Frank King <frank@wilsonvilleconcrete.com>
Date: Thu, Mar 12, 2020 at 9:26 PM
Subject: RE: 124 Berkley Ave. Row Permit
To: Gerardo Herrera <gsconcretework@gmail.com>
G,
The spec called out for a 6 sack mix, this mix is has a little more cement in it than the normal mix you use.
Let me know if you have any questions
Frank King
503-849-0079
Sales Manager
Wilsonville Concrete Products
PO Box 37
Wilsonville, OR 97070
Web: www.wilsonvilleconcrete.com
This electronic message transmission, including any attachments, contains information from Wilsonville Concrete Products which may be confidential or priveledged. The information is intended to be for the use of the individual or entity named above. If you are not the intended recipient, be aware that any disclosure, copying, distribution or use of the contents of this information is prohibited.
If you have received this electronic transmission in error, please notify the sender immediately by a "reply to sender only" message and destroy all electronic and hard copies of the communication, including attachments. Thank you, WCP
From: Gerardo Herrera <gsconcretework@gmail.com>
Sent: Thursday, March 12, 2020 2:32 PM
To: Frank King <frank@wilsonvilleconcrete.com>
Subject: Fwd: 124 Berkley Ave. Row Permit
---------- Forwarded message ---------
From: Sam Miller <smiller@cityofmolalla.com>
Date: Thu, Mar 12, 2020 at 12:31 PM
Subject: RE: 124 Berkley Ave. Row Permit
To: Gerardo Herrera <gsconcretework@gmail.com>
Good Afternoon Gerardo,
See attached file for your records. There are a few corrections and reinspection is required. I will also need a copy of the Concrete Mix Design before you pour. See note 1 on R-1095 for mix design min. standards. Please let me know if you have any questions. Thanks
Regards,
Sam Miller | Sr. Engineer Tech.
City of Molalla
117 N Molalla Ave. | PO Box 248 | Molalla, OR 97038
T : 503-759-0217 | E: smiller@cityofmolalla.com
From: Gerardo Herrera <gsconcretework@gmail.com>
Sent: Wednesday, January 8, 2020 9:49 PM
To: Sam Miller <smiller@cityofmolalla.com>
Subject: Re: 124 Berkley Ave. Row Permit
Sam
Thank you very much.
Gerardo Herrera with G's concrete inc.CCB#191032
On Tue, Jan 7, 2020 at 12:23 PM Sam Miller <smiller@cityofmolalla.com> wrote:
Good Afternoon,
See attach file of approved Row Permit PW65-2019 for your records. I have also attach the standards for concrete sidewalk and commercial driveway. Please let me know if you have any questions and make sure you schedule your inspection 24-48 hours in advance.
Regards,
Sam Miller | Sr. Engineer Tech.
City of Molalla
117 N Molalla Ave. | PO Box 248 | Molalla, OR 97038
T : 503-759-0217 | E: smiller@cityofmolalla.com
--
G's Concrete
Gerardo Herrera
503-891-5947
CLICK HERE for a special message from G
http://www.youtube.com/watch?v=JnnYbwLI1CQ
http://www.nwlocalcontractors.com/Concrete/G_s_Concrete_121.html
--
G's Concrete
Gerardo Herrera
503-891-5947
CLICK HERE for a special message from G
http://www.youtube.com/watch?v=JnnYbwLI1CQ
http://www.nwlocalcontractors.com/Concrete/G_s_Concrete_121.html
--
G's Concrete
Gerardo Herrera
503-891-5947
CLICK HERE for a special message from G
http://www.youtube.com/watch?v=JnnYbwLI1CQ
http://www.nwlocalcontractors.com/Concrete/G_s_Concrete_121.html
--
G's Concrete
Gerardo Herrera
503-891-5947
CLICK HERE for a special message from G
http://www.youtube.com/watch?v=JnnYbwLI1CQ
http://www.nwlocalcontractors.com/Concrete/G_s_Concrete_121.html