From: Sam Miller

Sent: Fri Nov 08 13:03:58 2019

To: Gerald Fisher

Subject: RE: 124 Berkley Project - Driveway

Importance: Normal

 

Thanks Gerald, do I need or would it be beneficial to take Pre Construction Photos or is that something that is require by the developer?

From: Gerald Fisher <gfisher@cityofmolalla.com>

Sent: Friday, November 8, 2019 9:20 AM

To: Sam Miller <smiller@cityofmolalla.com>

Subject: RE: 124 Berkley Project - Driveway

Hi Sam,

Here were the conditions of approval. The project file is in the following location.

Public Works\Engineering\Projects - Private\124 Berkley Ave (P50-2019)

Regards,

Gerald Fisher, P.E. | Public Works Director

City of Molalla

117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038

Office: 503.829.6855 | Direct: 503.759.0218

CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.

From: Gerald Fisher

Sent: Friday, November 8, 2019 9:19 AM

To: 'Karina Adams' <karina@kadamsarch.com>

Cc: Sam Miller (Molalla) <smiller@cityofmolalla.com>

Subject: RE: 124 Berkley Project - Driveway

Hi Karina,

This will work. Please have the contractor submit this plan with their PW permit application to Sam Miller, Sr. Engineering Tech. Thanks and have a good weekend.

Regards,

Gerald Fisher, P.E. | Public Works Director

City of Molalla

117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038

Office: 503.829.6855 | Direct: 503.759.0218

CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.

From: Karina Adams <karina@kadamsarch.com>

Sent: Thursday, November 7, 2019 4:57 PM

To: Gerald Fisher <gfisher@cityofmolalla.com>

Subject: Re: 124 Berkley Project - Driveway

Hi Gerald,

Would the attached be acceptable including the parking pad?

Thank you,

Karina

 

Karina Adams Architecture LLC

Residential & Commercial

Architecture and Interior Design

Portland and Surrounding Areas

www.KarinaAdamsArchitecture.com

503-753-2916

On Mon, Oct 28, 2019 at 9:29 AM Gerald Fisher <gfisher@cityofmolalla.com> wrote:

Hi Karina,

The 7 foot wing is to meet ADA with a conservative length. The design length is actually 6 feet but no concrete worker can meet the 1:12 slope requirement. You could drop the wing width down to 6.5 feet and reduce the driveway to 10 feet and we would give you an exception for the going below the standard provided that the business/property owner is OK and can utilize the reduced width. The only other option if a wider driveway is needed for business purposes is to relocate the PGE pole which is costly. Let me know what your client wants to do. Thanks.

Regards,

Gerald Fisher, P.E. | Public Works Director

City of Molalla

117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038

Office: 503.829.6855 | Direct: 503.759.0218

CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.

From: Karina Adams <karina@kadamsarch.com>

Sent: Tuesday, October 22, 2019 5:03 PM

To: Gerald Fisher <gfisher@cityofmolalla.com>

Subject: 124 Berkley Project - Driveway

Hi Gerald,

Per our conversation Friday, I have been looking at how to add a driveway to the 124 Berkley project. When we spoke, we were thinking we could get a driveway in between the power pole and the west property line. However, the pole is actually 26' from the property line. Even if I were to have them build the smallest 12 foot wide residential driveway, the 7' required Normals on either side of the driveway would put the concrete into the center of the power pole. Do you have an alternative options for me? Are there any exceptions to the 7' Normals or 12' minimum driveway?

Please see the attached sketch. I've bubbled the area I am speaking of.

Thank you,

Karina

 

Karina Adams Architecture LLC

Residential & Commercial

Architecture and Interior Design

Portland and Surrounding Areas

www.KarinaAdamsArchitecture.com

503-753-2916