From: Sam Miller

Sent: Fri Aug 06 10:45:46 2021

To: 'Cody Spanfellner'

Subject: RE: 118 N Cole Sewer connection

Importance: Normal

 

Thanks Cody,

The City requires the original copy for its records and will be released after final acceptance of the project, Please have you insurance company mail or hand deliver to City office, this needs to happen prior to start of construction on public infrastructure and material submittals. Thanks.

Regards,

Sam Miller | Sr. Engineer Tech.

City of Molalla

117 N Molalla Ave. | PO Box 248 | Molalla, OR 97038

T : 503-759-0217 | E: smiller@cityofmolalla.com

From: Cody Spanfellner <codybuilds@gmail.com>

Sent: Friday, August 6, 2021 9:59 AM

To: Sam Miller <smiller@cityofmolalla.com>

Subject: Re: 118 N Cole Sewer connection

Morning Sam,

The Surety Bond is attached for your records. All 3 bidders were between $12k to 15k for the water and sewer connections.

My insurance company said $30k bond is pretty standard for this type of work so that's what I did.

Let me know if you need any additional information.

Thanks, Cody

On Fri, Jul 30, 2021 at 8:25 AM Sam Miller <smiller@cityofmolalla.com> wrote:

Good Morning Cody,

See attached file for your records.

Regards,

Sam Miller | Sr. Engineer Tech.

City of Molalla

117 N Molalla Ave. | PO Box 248 | Molalla, OR 97038

T : 503-759-0217 | E: smiller@cityofmolalla.com

From: Cody Spanfellner <codybuilds@gmail.com>

Sent: Monday, July 19, 2021 1:45 PM

To: Sam Miller <smiller@cityofmolalla.com>

Subject: 118 N Cole Sewer connection

Hi Sam,

We are getting ready to start the project at 118 N Cole and the excavator and I would like to meet with you onsite to go over the sewer connection.

We are flexible on days but first thing in the morning would be best for us. If you can look at your schedule and let me know what works for you that would be great.

Thanks, and talk to you soon

Cody Spanfellner

--

Cody Spanfellner

Owner, CJS Builders Co.

503-539-0509

 

--

Cody Spanfellner

Owner, CJS Builders Co.

503-539-0509