From: Brenda Reiner

Sent: Tue Apr 03 09:17:04 2018

To: 'Sanitech'

Cc: Aldo Rodriguez

Subject: 117 Center

Importance: Normal

Attachments: PW Construction Permit Sheet - 2016.dotx;

 

Microsoft Exchange Server;converted from html;

Eric/Melissa,

There are a few items Engineering needs to process your PW Permit.

1. Do you have an engineer’s estimate for the public works construction piece?

2. Please fill out the PW Permit form (attached).

3. Do you have a contractor or will it be you?

4. We will need to have a precon before you start work.

5. The requirements are spelled out in the public works design and construction standards chapter 1.

6. We will also need a performance bond in the amount of 125% of the public improvements.

Thanks,

Brenda Reiner | Senior Engineering Technician

City of Molalla

117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038

Office: 503.759.0243 I Fax: 503.829.3676